Original Contract Amount
—
Revised Estimate
—
Total Certified to Date
—
Overall Progress
Project Information
Contract No.RDA/DRP/CEN/NUE/NUR/91
S/N91
Serial No.—
ProvinceCentral
DistrictNuwaraEliya
Implementing AgencyNorwood
Package No.5
Tender By—
Road NameApproach Road to Rozella Railway Station Road (B-027),Approa…
Contract DescriptionREHABILITATION/IMPROVEMENT APPROCH ROAD TO ROZELLA RAILWAY STATION (B-027)(0+000…
Estimated Road Lengths0.00 km
Number of Roads0
Number of Structures—
Chainage(0+000-3+300) …
Scope SummaryAsphalt overlay, Road Marking ,Retaining wall Construction,…
Scope & Duration
Commenced Date—
Scheduled Completion—
Possession of Site—
Contractor & Award
Contractor Name—
Tender StatusPending
LOA Date—
Contract Amount—
Estimate Amount—
Duration (Days)0
Tender Batch No.—