DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 6 awarded projects

2026-11-04
10:42:49Live2026-11-04
0 / 6Advance Pendingpending advance projects / total projects
2 / 6IPC Pendingpending IPC projects / total projects
0.0 Mn

— Mn

Advance Pend (incl. VAT)

19.5 Mn

19.55 Mn

IPCs Pend (incl. VAT)

Portfolio Breakdown — Financial (Exclusive Vat) · Emergency · EE: Nuwara Eliya · EE Office

129Projects22,610.7Contract Mn
Reset
Nuwara Eliya 6 projects Open filtered view
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency61,251.4304.624% of contract19.544157.6114100.584.3%20.6%
DC - Roads00.0——————————
DC - Slope00.0——————————
PD(CP) - Slope00.0——————————
Nuwara Eliya61,251.4304.624% of contract19.544157.6114100.584.3%20.6%
Emergency6 projects1,251.4Mn
24% paid304.6 Mn
Pending19.5Mn
Planned Fin84.3%
Actual Fin20.6%
Advance & IPC
Advance paid4 proj · 157.6 Mn
IPC paid4 proj · 100.5 Mn
Open filtered view
DC - Roads0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
Nuwara Eliya6 projects1,251.4Mn
24% paid304.6 Mn
Pending19.5Mn
Planned Fin84.3%
Actual Fin20.6%

Avg Physical Progress per Province · Emergency · EE: Nuwara Eliya

Project-wise Financials · Emergency · EE: Nuwara Eliya (171 Projects)

Clear EE

Project-wise Contract Value vs. Expenditure and Pending Payments · Emergency · EE: Nuwara Eliya (Mn · incl. VAT)

Scroll horizontally — 171 projects

Nuwara Eliya Division · Emergency · EE: Nuwara Eliya (Mn · incl. VAT)

Nuwara Eliya District Summary (Mn · incl. VAT)

District baseline — overall Emergency (consultant filter excluded for comparison) · amounts incl. VAT

Graphs reflect current view:6 awarded · Emergency · EE: Nuwara Eliya
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 171 projects

171–171/171

Filter financial register

171 matching projects

S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
171RDA/DC/DRP/SLOPE/CP/NUE/NOR/…
MITIGATION FOR FAILURE LOCATIONS ALONG AWISSAWELLA HATTON NUWARAELIYA ROAD (A007…
Finex Engineering (Pvt) Ltd
264,416,347.31————————————
Total34,005,299,486.172,738,852,403.053,231,645,820.60113,218,826.01133,598,214.691,049,943,508.601,238,847,524.5163,842,351.1873,647,937.023,788,795,911.65177,061,177.19
4,470.49Mn
13.1%
4,677.74Mn
13.8%
Showing 171–171 of 171 projects · page 18/18