DRRRP · Sri Lanka

Progress Ministry Report

Contract status summary for 171 awarded projects across Sri Lanka

Export XLSX
08:52:11Live2026-11-04
171

171

Awarded Projects

Active

135

In Progress (>0%)

Avg

35.6%

Avg Physical Progress

Mn

4,470.49

Total Financial Progress

Ministry Oversight

Progress Ministry Details

266 projects in current view

266/266

Filter ministry view

266 matching projects

Tiasa Construction (Pvt) Ltd

Delay
KandyKadugannawa182 days

Start

2026-03-25

Finish

2026-09-23

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

26.5%

Prev week: 25.0% +1.5%

Financial (Mn)

58.18

Critical Issues

—

Tap to viewView

Alucon Industries (Pvt) Ltd

KandyKandy182 days

Start

2026-09-01

Finish

2027-03-01

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

9%

Prev week: 7.7% +1.3%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Jayawansa Construction (Pvt) Ltd

KandyKandy182 days

Start

2026-09-09

Finish

2027-03-09

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

6%

Prev week: 5.3% +0.7%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Jayawansa Construction (Pvt) Ltd

KandyKandy182 days

Start

2026-09-17

Finish

2027-03-18

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

5%

Prev week: 4.8% +0.2%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Samindra Construction

KandyKundasale119 days

Start

2026-07-20

Finish

2026-11-15

LOA

Yes

Agreement Signed

Yes

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

53%

Prev week: 44.0% +9.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Jayasinghe Construction (Pvt) Ltd

Delay
KandyKundasale182 days

Start

2026-04-30

Finish

2026-10-28

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

12%

Prev week: 12.0%

Financial (Mn)

54.55

Critical Issues

—

Tap to viewView

SD Civil Construction (Pvt) Ltd

Delay
KandyKundasale182 days

Start

2026-03-25

Finish

2026-09-23

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

67%

Prev week: 62.0% +5.0%

Financial (Mn)

88.42

Critical Issues

—

Tap to viewView

Nimsara Construction & Engineering (Pvt) Ltd

KandyKundasale182 days

Start

2026-09-14

Finish

2027-03-14

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

5%

Prev week: 4.0% +1.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

S N O Builders (Pvt) Ltd

Delay
KandyKundasale119 days

Start

2026-07-06

Finish

2026-11-01

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

59%

Prev week: 57.0% +2.0%

Financial (Mn)

63.95

Critical Issues

—

Tap to viewView

SD Civil Construction (Pvt) Ltd

KandyKundasale126 days

Start

—

Finish

—

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Gihan Enterprise

Delay
KandyKundasale119 days

Start

2026-06-30

Finish

2026-10-27

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

66%

Prev week: 59.0% +7.0%

Financial (Mn)

27.21

Critical Issues

—

Tap to viewView

S N O Builders (Pvt) Ltd

KandyKundasale182 days

Start

2026-07-06

Finish

2027-01-03

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

61%

Prev week: 46.0% +15.0%

Financial (Mn)

37.29

Critical Issues

—

Tap to viewView

Alucon Industries (Pvt) Ltd

MataleMatale91 days

Start

2026-09-01

Finish

2026-11-30

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

7.5%

Prev week: 8.0% -0.5%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Lahiru Construction and Consultants (Pvt) Ltd

Delay
MataleMatale182 days

Start

2026-05-02

Finish

2026-10-30

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

68%

Prev week: 67.0% +1.0%

Financial (Mn)

89.58

Critical Issues

—

Tap to viewView

Jayasinghe Construction (Pvt) Ltd

Delay
MataleMatale91 days

Start

2026-05-02

Finish

2026-07-31

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

30%

Prev week: 29.0% +1.0%

Financial (Mn)

34.30

Critical Issues

—

Tap to viewView

Kanwel Constructions & Civil Engineering (Pvt) Ltd

Delay
MataleMatale182 days

Start

2026-05-02

Finish

2026-10-30

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

63%

Prev week: 62.0% +1.0%

Financial (Mn)

89.50

Critical Issues

—

Tap to viewView

Ediriweera Construction

MataleMatale182 days

Start

2026-07-30

Finish

2027-01-27

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

14%

Prev week: 13.0% +1.0%

Financial (Mn)

58.84

Critical Issues

—

Tap to viewView

Vikum Construction

MataleMatale182 days

Start

2026-09-02

Finish

2027-03-02

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

11%

Prev week: 10.0% +1.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

S A P Engineering (Pvt) Ltd

MataleNalanda154 days

Start

2026-10-02

Finish

2027-03-04

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

5%

Prev week: 0.0% +5.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Platinum Holdings Lanka (Private) Limited

MataleNalanda154 days

Start

2026-06-18

Finish

2026-11-18

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

70%

Prev week: 70.0%

Financial (Mn)

14.55

Critical Issues

—

Tap to viewView

Platinum Holdings Lanka (Private) Limited

Delay
MataleNalanda119 days

Start

2026-06-18

Finish

2026-10-14

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

90%

Prev week: 90.0%

Financial (Mn)

5.64

Critical Issues

—

Tap to viewView

Samindra Construction

Delay
Nuwara EliyaHanguranketha91 days

Start

2026-07-30

Finish

2026-10-28

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

30%

Prev week: 25.0% +5.0%

Financial (Mn)

9.25

Critical Issues

—

Tap to viewView

KSJ Construction (Pvt) Ltd

Nuwara EliyaNuwara Eliya182 days

Start

2026-10-07

Finish

2027-04-06

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

10%

Prev week: 8.0% +2.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

KSJ Construction (Pvt) Ltd

Delay
Nuwara EliyaNuwara Eliya91 days

Start

2026-05-02

Finish

2026-07-31

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

69%

Prev week: 68.0% +1.0%

Financial (Mn)

51.43

Critical Issues

—

Tap to viewView

KSJ Construction (Pvt) Ltd

Delay
Nuwara EliyaNuwara Eliya182 days

Start

2026-05-02

Finish

2026-10-30

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

78%

Prev week: 77.0% +1.0%

Financial (Mn)

101.99

Critical Issues

—

Tap to viewView

Green Scene Construction (Pvt) Ltd

Delay
Nuwara EliyaNuwara Eliya182 days

Start

2026-05-02

Finish

2026-10-30

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

40%

Prev week: 37.0% +3.0%

Financial (Mn)

52.80

Critical Issues

—

Tap to viewView

Southern Group Civil Construction (Pvt) Ltd

Delay
Nuwara EliyaNuwara Eliya182 days

Start

2026-05-02

Finish

2026-10-30

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

56%

Prev week: 54.0% +2.0%

Financial (Mn)

98.39

Critical Issues

—

Tap to viewView

Pragathi Civil Construction

Delay
Nuwara EliyaNuwara Eliya91 days

Start

2026-06-12

Finish

2026-09-10

LOA

Yes

Agreement Signed

Yes

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

20%

Prev week: 16.0% +4.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Jayawansa Construction (Pvt) Ltd

Delay
Nuwara EliyaNorwood91 days

Start

2026-06-17

Finish

2026-09-15

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

62%

Prev week: 60.0% +2.0%

Financial (Mn)

16.70

Critical Issues

—

Tap to viewView

Pragathi Civil Construction

Nuwara EliyaNorwood182 days

Start

2026-06-18

Finish

2026-12-16

LOA

Yes

Agreement Signed

Yes

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

44%

Prev week: 39.0% +5.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Sooriya Builders

Nuwara EliyaNorwood147 days

Start

2026-06-18

Finish

2026-11-11

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

31%

Prev week: 26.0% +5.0%

Financial (Mn)

17.35

Critical Issues

—

Tap to viewView

U.K.S Lanka Engineering (Pvt) Ltd

Nuwara EliyaNorwood365 days

Start

2026-07-30

Finish

2027-07-29

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

9%

Prev week: 6.0% +3.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

KDA Weerasinghe & Co (Pvt) Ltd

Nuwara EliyaNuwara Eliya546 days

Start

2026-09-17

Finish

2028-03-15

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

1%

Prev week: 3.0% -2.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Sanguine Engineering (Pvt) Ltd

KandyGampola301 days

Start

2026-09-03

Finish

2027-06-30

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

9.3%

Prev week: 3.5% +5.8%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Nagma Engineering (Pvt) Ltd

Nuwara EliyaNorwood364 days

Start

2026-09-16

Finish

2027-09-14

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

19%

Prev week: 16.0% +3.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

K.D.A. Weerasinghe & Co. (Pvt) Ltd

Nuwara EliyaNuwara Eliya546 days

Start

—

Finish

—

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Asset Engineering (Pvt) Ltd

Nuwara EliyaNuwara Eliya546 days

Start

—

Finish

—

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Asset Engineering (Pvt) Ltd

Nuwara EliyaNuwara Eliya546 days

Start

—

Finish

—

LOA

—

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Asset Engineering (Pvt) Ltd

Nuwara EliyaNuwara Eliya546 days

Start

—

Finish

—

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Nagma Engineering (Pvt) Ltd

Nuwara EliyaNuwara Eliya546 days

Start

—

Finish

—

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Weebadda Construction

KandyGampola105 days

Start

—

Finish

—

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

J. Kodithuwakkuarachchi & Sons (Pvt) Ltd

KandyGampola105 days

Start

—

Finish

—

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Bandaranayake Builders and Construction

KandyGampola105 days

Start

—

Finish

—

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Weebadda Construction

KandyGampola105 days

Start

—

Finish

—

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

J. Kodithuwakkuarachchi & Sons (Pvt) Ltd

KandyKundasale105 days

Start

—

Finish

—

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

J. Kodithuwakkuarachchi & Sons (Pvt) Ltd

KandyKundasale105 days

Start

—

Finish

—

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

J. Kodithuwakkuarachchi & Sons (Pvt) Ltd

KandyKundasale105 days

Start

—

Finish

—

LOA

—

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Weebadda Construction

KandyKadugannawa105 days

Start

—

Finish

—

LOA

—

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Tudawe Brothers (Pvt) Ltd

Delay
KegalleKegalle91 days

Start

2026-05-07

Finish

2026-08-05

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

65%

Prev week: 65.0%

Financial (Mn)

80.24

Critical Issues

—

Tap to viewView

Priyankara Industries & Contractors

Delay
BadullaBadulla180 days

Start

2026-03-26

Finish

2026-09-22

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

66%

Prev week: 65.5% +0.5%

Financial (Mn)

35.53

Critical Issues

—

Tap to viewView

EMA Construction (Pvt) Ltd

Delay
BadullaBadulla180 days

Start

2026-03-26

Finish

2026-09-21

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

79.5%

Prev week: 79.5%

Financial (Mn)

28.59

Critical Issues

—

Tap to viewView

K.E.P. Construction

Delay
RatnapuraRatnapura91 days

Start

2026-04-06

Finish

2026-07-06

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

31%

Prev week: 31.0%

Financial (Mn)

51.80

Critical Issues

—

Tap to viewView

Senura Civil Engineering (Pvt) Ltd

Delay
BadullaBadulla120 days

Start

2026-03-26

Finish

2026-09-23

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

40%

Prev week: 39.5% +0.5%

Financial (Mn)

50.41

Critical Issues

—

Tap to viewView

Subasingha Contractors (Pvt) Ltd

BadullaBadulla182 days

Start

2026-09-04

Finish

2027-03-05

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

12%

Prev week: 0.0% +12.0%

Financial (Mn)

47.71

Critical Issues

—

Tap to viewView

Creates Consultant and Construction

Delay
KegalleKegalle91 days

Start

2026-05-18

Finish

2026-08-16

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

60%

Prev week: 60.0%

Financial (Mn)

84.58

Critical Issues

—

Tap to viewView

EMA Construction (Pvt) Ltd

Delay
MonaragalaMonaragala180 days

Start

2026-04-06

Finish

2026-10-02

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

59%

Prev week: 59.0%

Financial (Mn)

32.06

Critical Issues

—

Tap to viewView

SSP Engineers (Pvt) Ltd

Delay
KegalleKegalle91 days

Start

2026-03-25

Finish

2026-06-25

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

70%

Prev week: 70.0%

Financial (Mn)

73.40

Critical Issues

—

Tap to viewView

Shabi Lanka Construction

BadullaBadulla126 days

Start

2026-09-04

Finish

2027-01-07

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

7%

Prev week: 0.0% +7.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

JD Builders

Delay
BadullaBadulla182 days

Start

2026-03-30

Finish

2026-09-27

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

71%

Prev week: 70.5% +0.5%

Financial (Mn)

23.01

Critical Issues

—

Tap to viewView

PH Engineering & Construction (Pvt) Ltd

Delay
BadullaBadulla182 days

Start

2026-03-30

Finish

2026-09-27

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

67.5%

Prev week: 67.5%

Financial (Mn)

68.46

Critical Issues

—

Tap to viewView

PH Engineering & Construction (Pvt) Ltd

Delay
BadullaBadulla182 days

Start

2026-03-27

Finish

2026-09-25

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

57.5%

Prev week: 57.5%

Financial (Mn)

64.35

Critical Issues

—

Tap to viewView

Senarathna Contractors

Delay
BadullaBadulla182 days

Start

2026-03-27

Finish

2026-09-24

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

73.5%

Prev week: 72.1% +1.4%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

SN Projects Lanka (Pvt) Ltd

Delay
RatnapuraRatnapura91 days

Start

2026-04-07

Finish

2026-07-07

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

22%

Prev week: 22.0%

Financial (Mn)

6.17

Critical Issues

—

Tap to viewView

SN Projects Lanka (Pvt) Ltd

Delay
RatnapuraRatnapura91 days

Start

2026-04-07

Finish

2026-07-07

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

26%

Prev week: 26.0%

Financial (Mn)

10.31

Critical Issues

—

Tap to viewView

Senarath Engineering (Pvt) Ltd

Delay
KegalleKegalle91 days

Start

2026-05-29

Finish

2026-08-29

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

75%

Prev week: 75.0%

Financial (Mn)

86.19

Critical Issues

—

Tap to viewView

Solinro Builders

RatnapuraRatnapura91 days

Start

2026-04-07

Finish

2026-07-07

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

100%

Prev week: 100.0%

Financial (Mn)

64.68

Critical Issues

—

Tap to viewView

Keangnam Engineering & Construction (Pvt) Ltd

Delay
RatnapuraRatnapura91 days

Start

2026-03-27

Finish

2026-06-26

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

42.9%

Prev week: 43.0% -0.1%

Financial (Mn)

71.92

Critical Issues

—

Tap to viewView

SSP Engineers (Pvt) Ltd

Delay
RatnapuraRatnapura91 days

Start

2026-04-07

Finish

2026-07-07

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

85.8%

Prev week: 86.0% -0.2%

Financial (Mn)

99.99

Critical Issues

—

Tap to viewView

Wijeratne Construction

Delay
RatnapuraRatnapura91 days

Start

2026-04-07

Finish

2026-07-07

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

62%

Prev week: 62.0%

Financial (Mn)

85.49

Critical Issues

—

Tap to viewView

Kanwel Constructions & Civil Engineering (Pvt) Ltd

Delay
BadullaBadulla182 days

Start

2026-03-26

Finish

2026-09-23

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

61%

Prev week: 60.5% +0.5%

Financial (Mn)

84.20

Critical Issues

—

Tap to viewView

Kanwel Constructions & Civil Engineering (Pvt) Ltd

Delay
BadullaBadulla182 days

Start

2026-03-26

Finish

2026-09-24

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

57%

Prev week: 50.5% +6.5%

Financial (Mn)

66.48

Critical Issues

—

Tap to viewView

Samdam Engineering & Constructions (Pvt) Ltd

Delay
RatnapuraRatnapura91 days

Start

2026-04-06

Finish

2026-07-06

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

32%

Prev week: 32.0%

Financial (Mn)

58.44

Critical Issues

—

Tap to viewView

Subasingha Contractors (Pvt) Ltd

Delay
BadullaBadulla182 days

Start

2026-04-02

Finish

2026-09-30

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

66%

Prev week: 62.0% +4.0%

Financial (Mn)

82.60

Critical Issues

—

Tap to viewView

Suhada Enterprises

Delay
BadullaBadulla182 days

Start

2026-03-27

Finish

2026-09-24

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

77%

Prev week: 69.0% +8.0%

Financial (Mn)

65.48

Critical Issues

—

Tap to viewView

Ediriweera Construction

Delay
MonaragalaMonaragala182 days

Start

2026-04-07

Finish

2026-10-05

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

51%

Prev week: 48.0% +3.0%

Financial (Mn)

27.10

Critical Issues

—

Tap to viewView

SSP Engineers (Pvt) Ltd

Delay
RatnapuraRatnapura91 days

Start

2026-04-07

Finish

2026-06-24

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

85%

Prev week: 85.0%

Financial (Mn)

86.13

Critical Issues

—

Tap to viewView

Southern Group Civil Construction (Pvt) Ltd

Delay
KegalleKegalle91 days

Start

2026-06-10

Finish

2026-09-11

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

50%

Prev week: 50.0%

Financial (Mn)

66.81

Critical Issues

—

Tap to viewView

KENT Engineering (Pvt) Ltd

KegalleKegalle154 days

Start

2026-09-11

Finish

2027-02-12

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

KENT Engineering (Pvt) Ltd

KegalleKegalle182 days

Start

2026-09-11

Finish

2027-03-12

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Southern Group Civil Construction (Pvt) Ltd

Delay
KegalleKegalle91 days

Start

2026-06-10

Finish

2026-09-11

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

25%

Prev week: 25.0%

Financial (Mn)

41.33

Critical Issues

—

Tap to viewView

SMA Construction (Pvt) Ltd

Delay
AnuradhapuraAnuradhapura182 days

Start

2026-04-20

Finish

2026-10-19

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

50%

Prev week: 50.0%

Financial (Mn)

25.54

Critical Issues

—

Tap to viewView

SMA Construction (Pvt) Ltd

Delay
AnuradhapuraAnuradhapura182 days

Start

2026-04-20

Finish

2026-10-19

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

38%

Prev week: 38.0%

Financial (Mn)

27.26

Critical Issues

—

Tap to viewView

Tudawe Brothers (Pvt) Ltd

Delay
GampahaGampaha182 days

Start

2026-05-04

Finish

2026-11-02

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

20%

Prev week: 20.0%

Financial (Mn)

44.19

Critical Issues

—

Tap to viewView

Tudawe Brothers (Pvt) Ltd

Delay
GampahaGampaha182 days

Start

2026-05-04

Finish

2026-11-02

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

28%

Prev week: 26.0% +2.0%

Financial (Mn)

46.35

Critical Issues

—

Tap to viewView

Senarath Engineering (Pvt) Ltd

Delay
GampahaGampaha91 days

Start

2026-04-24

Finish

2026-07-24

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

2%

Prev week: 2.0%

Financial (Mn)

19.76

Critical Issues

—

Tap to viewView

Senarath Engineering (Pvt) Ltd

Delay
GampahaGampaha91 days

Start

2026-04-24

Finish

2026-07-24

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

2%

Prev week: 2.0%

Financial (Mn)

32.53

Critical Issues

—

Tap to viewView

Jeyanthan Construction

Delay
GampahaGampaha91 days

Start

2026-06-04

Finish

2026-09-03

LOA

Yes

Agreement Signed

Yes

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

46%

Prev week: 44.0% +2.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Senarath Engineering (Pvt) Ltd

Delay
GampahaGampaha182 days

Start

2026-04-24

Finish

2026-10-23

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

1%

Prev week: 1.0%

Financial (Mn)

56.23

Critical Issues

—

Tap to viewView

Senarath Engineering (Pvt) Ltd

Delay
GampahaGampaha182 days

Start

2026-04-24

Finish

2026-10-23

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

1%

Prev week: 1.0%

Financial (Mn)

53.99

Critical Issues

—

Tap to viewView

Accon Engineering (Pvt) Ltd

Delay
KegalleKegalle91 days

Start

2026-05-22

Finish

2026-08-21

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

68%

Prev week: 68.0%

Financial (Mn)

47.71

Critical Issues

—

Tap to viewView

Tudawe Brothers (Pvt) Ltd

Delay
KegalleKegalle91 days

Start

2026-06-01

Finish

2026-08-31

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

18%

Prev week: 18.0%

Financial (Mn)

68.13

Critical Issues

—

Tap to viewView

Keangnam Engineering & Construction (Pvt) Ltd

Delay
ColomboColombo91 days

Start

2026-04-21

Finish

2026-07-21

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

29%

Prev week: 29.0%

Financial (Mn)

8.06

Critical Issues

—

Tap to viewView

Keangnam Engineering & Construction (Pvt) Ltd

Delay
ColomboColombo63 days

Start

2026-04-21

Finish

2026-06-23

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

3%

Prev week: 3.0%

Financial (Mn)

1.44

Critical Issues

—

Tap to viewView

Keangnam Engineering & Construction (Pvt) Ltd

Delay
ColomboColombo63 days

Start

2026-04-21

Finish

2026-06-23

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

65%

Prev week: 65.0%

Financial (Mn)

55.94

Critical Issues

—

Tap to viewView

Keangnam Engineering & Construction (Pvt) Ltd

Delay
ColomboColombo63 days

Start

2026-04-21

Finish

2026-06-23

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

3%

Prev week: 3.0%

Financial (Mn)

1.93

Critical Issues

—

Tap to viewView

Can Construction and Consultancy (Pvt) Ltd

KurunegalaKurunegala119 days

Start

2026-08-28

Finish

2026-12-25

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

12%

Prev week: 11.0% +1.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Can Construction and Consultancy (Pvt) Ltd

KurunegalaKurunegala91 days

Start

2026-09-11

Finish

2027-03-11

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Jayawansa Construction (Pvt) Ltd

KurunegalaKurunegala91 days

Start

2026-09-29

Finish

2027-03-29

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

TMC Construction (Pvt) Ltd

Delay
KurunegalaKurunegala91 days

Start

2026-04-21

Finish

2026-07-22

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

62%

Prev week: 65.0% -3.0%

Financial (Mn)

32.34

Critical Issues

—

Tap to viewView

St. Anthony's Construction

Delay
KurunegalaKurunegala119 days

Start

2026-05-05

Finish

2026-09-01

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

70%

Prev week: 70.0%

Financial (Mn)

32.51

Critical Issues

—

Tap to viewView

SSP Engineers (Pvt) Ltd

Delay
RatnapuraRatnapura91 days

Start

2026-05-15

Finish

2026-08-14

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

62%

Prev week: 62.0%

Financial (Mn)

89.82

Critical Issues

—

Tap to viewView

Anura Construction

Delay
RatnapuraRatnapura91 days

Start

2026-04-24

Finish

2026-07-24

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

21%

Prev week: 21.0%

Financial (Mn)

55.58

Critical Issues

—

Tap to viewView

Samarasinghe Construction Pvt Ltd

RatnapuraRatnapura182 days

Start

2026-09-11

Finish

2027-03-12

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

3%

Prev week: 0.0% +3.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Southern Group Civil Construction (Pvt) Ltd

Delay
Trincomalee—182 days

Start

2026-05-06

Finish

2026-11-02

LOA

Yes

Agreement Signed

Yes

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

20%

Prev week: —

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Nathans Construction

Delay
Trincomalee—182 days

Start

2026-05-06

Finish

2026-11-02

LOA

Yes

Agreement Signed

Yes

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

82%

Prev week: —

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Jayasinghe Construction (Pvt) Ltd

Delay
ColomboColombo91 days

Start

2026-05-10

Finish

2026-08-09

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

5%

Prev week: 5.0%

Financial (Mn)

31.05

Critical Issues

—

Tap to viewView

Jayasinghe Construction (Pvt) Ltd

Delay
ColomboColombo91 days

Start

2026-05-10

Finish

2026-08-09

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

5%

Prev week: 5.0%

Financial (Mn)

33.25

Critical Issues

—

Tap to viewView

Greenwawe Construction (Pvt) Ltd

Delay
ColomboColombo63 days

Start

2026-05-10

Finish

2026-07-12

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

26%

Prev week: 26.0%

Financial (Mn)

58.02

Critical Issues

—

Tap to viewView

Kanwel Constructions & Civil Engineering (Pvt) Ltd

Delay
BadullaBadulla182 days

Start

2026-05-06

Finish

2026-11-03

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

50%

Prev week: 47.0% +3.0%

Financial (Mn)

44.89

Critical Issues

—

Tap to viewView

Suhada Enterprises

Delay
BadullaBadulla182 days

Start

2026-05-06

Finish

2026-11-03

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

56%

Prev week: 49.0% +7.0%

Financial (Mn)

75.36

Critical Issues

—

Tap to viewView

Abeywardhana Construction

Delay
PolonnaruwaPolonnaruwa91 days

Start

2026-06-05

Finish

2026-05-08

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

56%

Prev week: 56.0%

Financial (Mn)

31.02

Critical Issues

—

Tap to viewView

Anura Construction

Delay
RatnapuraRatnapura91 days

Start

2026-05-10

Finish

2026-08-09

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

15%

Prev week: 15.0%

Financial (Mn)

55.17

Critical Issues

—

Tap to viewView

Kanwel Constructions & Civil Engineering (Pvt) Ltd

Delay
RatnapuraRatnapura91 days

Start

2026-05-10

Finish

2026-08-11

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

23.7%

Prev week: 24.0% -0.3%

Financial (Mn)

69.09

Critical Issues

—

Tap to viewView

S S K Construction

Delay
Batticaloa—91 days

Start

2026-05-25

Finish

2026-08-24

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

70%

Prev week: 0.0% +70.0%

Financial (Mn)

53.42

Critical Issues

—

Tap to viewView

Jayanetti Construction

BadullaBadulla182 days

Start

2026-05-25

Finish

2026-11-22

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

70%

Prev week: 70.0%

Financial (Mn)

57.88

Critical Issues

—

Tap to viewView

Nimsara Construction & Engineering (Pvt) Ltd

BadullaBadulla182 days

Start

2026-05-25

Finish

2026-11-22

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

66%

Prev week: 65.5% +0.5%

Financial (Mn)

53.97

Critical Issues

—

Tap to viewView

SF Construction (Pvt) Ltd

BadullaBadulla210 days

Start

2026-05-25

Finish

2026-12-20

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

48.5%

Prev week: 48.5%

Financial (Mn)

40.16

Critical Issues

—

Tap to viewView

SF Construction (Pvt) Ltd

BadullaBadulla182 days

Start

2026-05-25

Finish

2026-11-22

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

66.5%

Prev week: 66.5%

Financial (Mn)

62.20

Critical Issues

—

Tap to viewView

Anura Construction

Delay
RatnapuraRatnapura91 days

Start

2026-06-29

Finish

2026-09-28

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

10%

Prev week: 10.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Anura Construction

Delay
RatnapuraRatnapura91 days

Start

2026-06-29

Finish

2026-09-28

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

10%

Prev week: 10.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Anura Construction

Delay
RatnapuraRatnapura91 days

Start

2026-06-29

Finish

2026-09-28

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

15%

Prev week: 15.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Anura Construction

Delay
RatnapuraRatnapura91 days

Start

2026-05-09

Finish

2026-08-28

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

6%

Prev week: 6.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

D K S Construction

Delay
RatnapuraRatnapura91 days

Start

2026-07-01

Finish

2026-09-30

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

42%

Prev week: 42.0%

Financial (Mn)

58.10

Critical Issues

—

Tap to viewView

INK Engineering

Delay
ColomboColombo91 days

Start

2026-05-25

Finish

2026-08-24

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

12%

Prev week: 12.0%

Financial (Mn)

6.46

Critical Issues

—

Tap to viewView

Motec Engineering & Construction

Trincomalee—182 days

Start

2026-06-02

Finish

2026-12-01

LOA

Yes

Agreement Signed

Yes

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

40%

Prev week: —

Financial (Mn)

17.94

Critical Issues

—

Tap to viewView

Motec Engineering & Construction

Delay
Trincomalee—63 days

Start

2026-06-02

Finish

2026-08-04

LOA

Yes

Agreement Signed

Yes

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

65%

Prev week: —

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

RCDC Construction Company (Pvt) Ltd

Kurunegala—91 days

Start

2026-10-07

Finish

2027-02-09

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

6%

Prev week: 6.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

ST MARY Construction

Delay
PuttalamChilaw63 days

Start

2026-06-12

Finish

2026-08-15

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

56%

Prev week: 56.0%

Financial (Mn)

17.97

Critical Issues

—

Tap to viewView

Ranuja Construction

Delay
AnuradhapuraAnuradhapura91 days

Start

2026-07-23

Finish

2026-10-22

LOA

Yes

Agreement Signed

Yes

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

16%

Prev week: 16.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Lahiru Construction and Consultants (Pvt) Ltd

Delay
PolonnaruwaPolonnaruwa91 days

Start

2026-02-06

Finish

2026-01-09

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

90%

Prev week: 90.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

NMST Contractors

AnuradhapuraAnuradhapura91 days

Start

2026-08-28

Finish

2026-11-27

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

12%

Prev week: 12.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

W.M.B. Contractors & Transporter

Delay
AnuradhapuraAnuradhapura91 days

Start

2026-06-30

Finish

2026-09-29

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

90%

Prev week: 90.0%

Financial (Mn)

40.73

Critical Issues

—

Tap to viewView

The Crown Construction

Delay
AnuradhapuraAnuradhapura91 days

Start

2026-02-06

Finish

2026-01-09

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

47%

Prev week: 47.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

DKS Nishantha Construction

Delay
RatnapuraRatnapura91 days

Start

2026-06-12

Finish

2026-09-12

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

60%

Prev week: 41.0% +19.0%

Financial (Mn)

19.17

Critical Issues

—

Tap to viewView

AKC Construction

RatnapuraRatnapura182 days

Start

2026-06-12

Finish

2026-12-11

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

45%

Prev week: 45.0%

Financial (Mn)

10.99

Critical Issues

—

Tap to viewView

Jayawansa Construction (Pvt) Ltd

PuttalamChilaw182 days

Start

2026-07-22

Finish

2027-01-20

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

28%

Prev week: 25.0% +3.0%

Financial (Mn)

44.99

Critical Issues

—

Tap to viewView

RCDC Construction Company (Pvt) Ltd

PuttalamChilaw182 days

Start

2026-09-29

Finish

2027-03-29

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

5%

Prev week: 0.0% +5.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

ST MARY Construction

PuttalamChilaw182 days

Start

2026-06-02

Finish

2026-12-01

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

14%

Prev week: 11.0% +3.0%

Financial (Mn)

27.43

Critical Issues

—

Tap to viewView

Omega Construction Company (Pvt) Ltd

PuttalamChilaw182 days

Start

2026-06-02

Finish

2026-12-01

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

35%

Prev week: 33.0% +2.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

D K S Construction

Delay
Badulla—119 days

Start

2026-06-20

Finish

2026-10-17

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

44.5%

Prev week: 42.0% +2.5%

Financial (Mn)

60.53

Critical Issues

—

Tap to viewView

Sawsiri Construction

PolonnaruwaPolonnaruwa91 days

Start

2026-02-06

Finish

2026-01-09

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

100%

Prev week: 100.0%

Financial (Mn)

11.64

Critical Issues

—

Tap to viewView

A.D.M Construction

Delay
PolonnaruwaPolonnaruwa91 days

Start

2026-02-06

Finish

2026-01-09

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

55%

Prev week: 55.0%

Financial (Mn)

13.06

Critical Issues

—

Tap to viewView

Gamage Builders

Badulla—182 days

Start

2026-07-01

Finish

2026-12-30

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

36%

Prev week: 30.0% +6.0%

Financial (Mn)

61.67

Critical Issues

—

Tap to viewView

Ediriweera Construction

Delay
Ampara—91 days

Start

2026-06-12

Finish

2026-09-10

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

90%

Prev week: 78.0% +12.0%

Financial (Mn)

5.95

Critical Issues

—

Tap to viewView

Jeezan Trading and Transport

Ampara—182 days

Start

2026-06-12

Finish

2026-12-10

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

29%

Prev week: 27.0% +2.0%

Financial (Mn)

18.24

Critical Issues

—

Tap to viewView

Nazeeha Hardware and Construction

Ampara—182 days

Start

2026-06-12

Finish

2026-12-10

LOA

Yes

Agreement Signed

Yes

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

23%

Prev week: 19.0% +4.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Omega Construction Company (Pvt) Ltd

PuttalamChilaw182 days

Start

2026-06-18

Finish

2026-12-17

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

26%

Prev week: 26.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Venus Enterprise

Delay
GampahaGampaha91 days

Start

2026-06-18

Finish

2026-09-17

LOA

Yes

Agreement Signed

Yes

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

60%

Prev week: 55.0% +5.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

A.D.M Construction

Delay
PolonnaruwaPolonnaruwa91 days

Start

2026-07-12

Finish

2026-09-11

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

40%

Prev week: 40.0%

Financial (Mn)

8.95

Critical Issues

—

Tap to viewView

Anura Construction

RatnapuraRatnapura91 days

Start

2026-08-13

Finish

2026-12-11

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

D K S Construction

Badulla—182 days

Start

2026-07-03

Finish

2027-01-07

LOA

Yes

Agreement Signed

Yes

Account Open

Yes

Advance Paid

Yes

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

21%

Prev week: 18.0% +3.0%

Financial (Mn)

68.55

Critical Issues

—

Tap to viewView

Ceylon Construction Industry Development (Pvt) Ltd

GalleGalle63 days

Start

2026-07-06

Finish

2026-09-07

LOA

Yes

Agreement Signed

Yes

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

100%

Prev week: 100.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Ceylon Construction Industry Development (Pvt) Ltd

Delay
GalleGalle91 days

Start

2026-07-06

Finish

2026-10-05

LOA

Yes

Agreement Signed

Yes

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

98%

Prev week: 95.0% +3.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Nimna Holdings (Pvt) Ltd

Badulla—182 days

Start

2026-09-04

Finish

2027-03-05

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

16%

Prev week: 12.0% +4.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

SSK Construction

Kilinochchi—91 days

Start

2026-09-07

Finish

2026-12-07

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

6%

Prev week: 6.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Asset Engineering (Pvt) Ltd

Mannar—119 days

Start

2026-08-27

Finish

2026-12-23

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Jana Civil Work Contractors & Material Suppliers

MullaitivuMullaitivu91 days

Start

2026-08-27

Finish

2026-11-25

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

10%

Prev week: 10.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Jana Civil Work Contractors & Material Suppliers

VavuniyaVavuniya119 days

Start

2026-08-27

Finish

2026-12-23

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

Yes

Mobilized

Yes

In Progress

Yes

Physical Progress Up To this Week

18%

Prev week: 17.0% +1.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

S S K Construction

JaffnaJaffna154 days

Start

2026-10-20

Finish

2027-03-23

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Nimna Holdings (Pvt) Ltd

JaffnaJaffna—

Start

—

Finish

—

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

A.D.M Construction

TrincomaleeTrincomalee—

Start

—

Finish

—

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Komuthi Engineering Services (Pvt) Ltd

Gampaha—243 days

Start

—

Finish

—

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Sanguine Engineering (Pvt) Ltd

MataleMatale301 days

Start

—

Finish

—

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Sanguine Engineering (Pvt) Ltd

Nuwara EliyaNuwara Eliya273 days

Start

—

Finish

—

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Finex Engineering (Pvt) Ltd

KandyKundasale364 days

Start

—

Finish

—

LOA

Yes

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

HMA Enterprises (Pvt) Ltd

Nuwara EliyaNorwood273 days

Start

—

Finish

—

LOA

—

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Nagma Engineering (Pvt) Ltd

Nuwara EliyaNuwara Eliya273 days

Start

—

Finish

—

LOA

—

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: —

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

HMA Enterprises (Pvt) Ltd

KandyKadugannawa273 days

Start

—

Finish

—

LOA

—

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: 0.0%

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Nagma Engineering (Pvt) Ltd

Nuwara EliyaHanguranketha273 days

Start

—

Finish

—

LOA

—

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: —

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Finex Engineering (Pvt) Ltd

Nuwara EliyaHanguranketha273 days

Start

—

Finish

—

LOA

—

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: —

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Finex Engineering (Pvt) Ltd

Nuwara EliyaNorwood273 days

Start

—

Finish

—

LOA

—

Agreement Signed

—

Account Open

—

Advance Paid

—

Kick Off

—

Mobilized

—

In Progress

—

Physical Progress Up To this Week

0%

Prev week: —

Financial (Mn)

0.00

Critical Issues

—

Tap to viewView

Totals (171 projects)

Duration

27,287

Avg Progress

32.9%

Financial

4,470.49