RDA/DRP/NWP/KURU/KURU/03R
Rehabilitation / Improvement of Thalgodapitiya Yatawaththa Road (B409) (9+100 - 14+650)
KurunegalaNorth Western ProvinceKurunegalaDivisional SecretariatJayawansa Construction (Pvt) LtdContractorLKR 129,109,243.85Contract Sum91 daysProject Duration
0%
Complete
Physical Progress0%
Planned Progress38.3%
Time Elapsed39.6%
On Track145days left
On Track • 145 days left
Project Timeline
LOA
–
PendingPossession
–
PendingCommencement
2026-09-29
CompletedScheduled Completion
2027-03-29
On TrackAnticipated Completion Date
–
PendingSwipe tabs to see all sections — tap to switch
Location & Package
ProvinceNorth Western Province
DistrictKurunegala
PD RegionNorth Western Province
CE RegionKurunegala
EE DivisionKurunegala
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Thalgodapitiya Yatawaththa Road (B409) (9+100 - 14+650)
Estimated Road Lengths- km
Number of Roads-
Scope SummaryConstruction of toe walls
Construction of gabion walls
Construction of gabion walls
Contractor & Award
Contract No.RDA/DRP/NWP/KURU/KURU/03R
Tender Batch No.15
Contractor NameJayawansa Construction (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date—
Contract Amount129,109,243.85
Engineer Estimate Amount (LKR)117,113,346.84
Duration (Days)91
CategoryEmergency
IPC 1Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 2Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 3Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 4Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 5Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 6Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 7Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 8Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 9Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 10Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 11Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 12Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 13Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 14Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 15Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 16Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 17Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 18Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 19Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 20Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount