DRRRP Awarded Emergency

RDA/DRP/UVA/BAD/BAD/03

Rehabilitation / Improvement of Peradeniya Badulla Chenkaladi Road (90+000-123+000) (AA-005)

BadullaUva ProvinceBadullaDivisional SecretariatKanwel Constructions & Civil Engineering (Pvt) LtdContractorLKR 277,749,116.37Contract Sum182 daysProject Duration
61%
Complete
Physical Progress61%
Planned Progress100%
Time Elapsed100%
42 days behind schedule

Project Timeline

LOA
2026-03-12
Completed
Possession
–
Pending
Commencement
2026-03-26
Completed
Scheduled Completion
2026-09-23
Completed
Anticipated Completion Date
2026-09-23
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceUva Province
DistrictBadulla
PD RegionUva Province
CE RegionBadulla
EE DivisionBadulla
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Peradeniya Badulla Chenkaladi Road (90+000-123+000) (AA-005)
Estimated Road Lengths- km
Number of Roads-
Scope SummaryRetainining structures, Drainage construction
Contractor & Award
Contract No.RDA/DRP/UVA/BAD/BAD/03
Tender Batch No.3
Contractor NameKanwel Constructions & Civil Engineering (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date2026-03-12
Contract Amount277,749,116.37
Engineer Estimate Amount (LKR)282,102,670.39
Duration (Days)182