Rehabilitation / Improvement of Malwala - Carney Road (Ch. 11+000 - Ch. 14+972)
RatnapuraSabaragamuwa ProvinceRatnapuraDivisional SecretariatSSP Engineers (Pvt) LtdContractorLKR 184,511,228.94Contract Sum91 daysProject Duration
Schedule Delay120 daysbehind schedule
120 days behind schedule
Commencement
2026-04-07
Completed
Scheduled Completion
2026-07-07
Completed
Anticipated Completion Date
2026-07-07
Delayed Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceSabaragamuwa Province
DistrictRatnapura
PD RegionSabaragamuwa Province
CE RegionRatnapura
EE DivisionRatnapura
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Malwala - Carney Road (Ch. 11+000 - Ch. 14+972)
Estimated Road Lengths- km
Number of Roads-
Scope Summary4 km Asphalt Overlaying, Culvert Construction (Widening -18, Reconstrction - 5)
Contractor & Award
Contract No.RDA/DRP/SAB/RAT/RAT/26
Tender Batch No.2
Contractor NameSSP Engineers (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date2026-03-13
Contract Amount184,511,228.94
Engineer Estimate Amount (LKR)199,494,622.85
Duration (Days)91
CategoryEmergency
Document Readiness
5 of 12 required documents received.
5 Received7 Pending
Contractual5/7
LOA IssuedYes
Agreement SignedYes
Escrow AgreementYes
Performance BondYes
Contract Doc. Received—
Insurance—
Advance BondYes
Technical0/5
Source Approval Request—
Drawings Submitted—
Contractor Staff Details—
Work Programme—
Traffic Mgmt & Safety Plan—
Contract Period Timeline
Scheduled Completion
2026-07-07
Anticipated Completion Date
2026-07-07
Duration Elapsed211 / 91 days
Schedule Status120 Days in Delay
Anticipated Completion Date2026-07-07
Project Completed—
Completed Date—
Mobilization
Planned vs Actual
Physical Progress85.8% vs 100%
Financial Progress45.9% vs 100%
Progress MonitorCritical Delay
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 21.3% of contract
IPC 1 (Advance)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
PD Certified2026-06-25
LKR 33,247,096.15LKR 39,231,573.46DateAmount (excl. VAT)Amount (incl. VAT)
Advance Summary
Advance BondYes
Advance PaidYes
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 45.9% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
IPC 2 (IPC)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
PD Certified2026-06-25
LKR 11,825,244.19LKR 13,953,788.15DateAmount (excl. VAT)Amount (incl. VAT)
IPC 3 (IPC)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
PD Certified2026-08-10
LKR 16,388,617.67LKR 19,338,568.85DateAmount (excl. VAT)Amount (incl. VAT)
IPC 4 (IPC)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
PD Certified2026-09-02
LKR 5,714,479.90LKR 6,743,086.28DateAmount (excl. VAT)Amount (incl. VAT)
IPC 5 (IPC)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
PD Certified2026-10-06
LKR 2,702,636.35LKR 3,189,110.89DateAmount (excl. VAT)Amount (incl. VAT)
IPC 6 (IPC)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
PD Certified2026-10-06
LKR 14,861,776.35LKR 17,536,896.09DateAmount (excl. VAT)Amount (incl. VAT)
IPC 7Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 8Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 9Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 10Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 11Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 12Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 13Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 14Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 15Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 16Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 17Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 18Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 19Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 20Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 21Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 22Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 23Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 24Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 25Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 26Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Revised Contract
contract + approved VOs
No variations recorded
This project has no variation orders yet.
EOTs
0 approved · 0 pending
Days Requested
across 0 EOTs
Approved Days
0 approved EOTs
Revised Finish
planned 2026-07-07
No extensions recorded
This project has no extension-of-time requests yet.
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
Yes - projects.advance_bondBank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
Time
Elapsed - 120 Days in Delay
Overall Progress
Overall
Planned: 100%Behind by 14.2%
Financial Actual: 84.74 Mn / Planned 184.51 MnBehind 99.77 Mn
Critical Issues-
Ratnapura - Ratnapura
Rehabilitation / Improvement of Malwala - Carney Road (Ch. 11+000 - Ch. 14+972)
Project Name:
Project #172 - Contract No. RDA/DRP/SAB/RAT/RAT/26
Physical S-Curve - 2026-11-04 - Generated 2026-11-04 08:54
Contract No. RDA/DRP/SAB/RAT/RAT/26
Physical S-Curve - Planned vs Actual
Today: 2026-11-04 - 85.8%
Weekly Planned (Physical %)
Presentage
Actual financial
Ratnapura - Ratnapura
Rehabilitation / Improvement of Malwala - Carney Road (Ch. 11+000 - Ch. 14+972)
Project Name:
Project #172 - Contract No. RDA/DRP/SAB/RAT/RAT/26
Financial S-Curve - 2026-11-04 - Generated 2026-11-04 08:54
Contract No. RDA/DRP/SAB/RAT/RAT/26
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-11-04 - LKR 84.74 Mn
Weekly Planned (Financial Mn)
Documents & Attachments
0 file(s) - up to 25 MB each
| Title | Category | Uploaded By | Size | Date | Actions |
|---|
| No documents uploaded. |
Completion Forecast
Add at least 2 weekly progress snapshots to forecast completion.
Weekly Digest
Last snapshot2026-11-02
Snapshot value85.8%
Current progress85.8%
Change+0%