DRRRP Awarded Emergency

RDA/DRP/NWP/CHI/CHI/08

Rehabilitation / Improvement of Baththuluoya - Udappuwa - Andimunai Road (B614) at 6+100 in Chilaw EE Division

PuttalamNorth Western ProvinceChilawDivisional SecretariatST MARY ConstructionContractorLKR 83,944,711.21Contract Sum63 daysProject Duration
56%
Complete
Physical Progress56%
Planned Progress100%
Time Elapsed100%
81 days behind schedule

Project Timeline

LOA
2026-05-20
Completed
Possession
–
Pending
Commencement
2026-06-12
Completed
Scheduled Completion
2026-08-15
Completed
Anticipated Completion Date
2026-10-14
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceNorth Western Province
DistrictPuttalam
PD RegionNorth Western Province
CE RegionChilaw
EE DivisionChilaw
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Baththuluoya - Udappuwa - Andimunai Road (B614) at 6+100 in Chilaw EE Division
Estimated Road Lengths- km
Number of Roads-
Scope SummarySlope protection for embankement, const. of hard shoulder, Construction of U drains
Contractor & Award
Contract No.RDA/DRP/NWP/CHI/CHI/08
Tender Batch No.9
Contractor NameST MARY Construction
Consultant-
Tender StatusAwarded
LOA Date2026-05-20
Contract Amount83,944,711.21
Engineer Estimate Amount (LKR)84,197,870.47
Duration (Days)63
CategoryEmergency