DRRRP Awarded Emergency

RDA/DRP/NWP/KURU/MAHO/06R

Rehabilitation / Improvement of Kadigawa Bridge Approaches on Pahala Mawathagama - Kadigawa Road (0+000-0+175)

KurunegalaNorth Western Province-Divisional SecretariatRCDC Construction Company (Pvt) LtdContractorLKR 75,025,358.95Contract Sum91 daysProject Duration
6%
Complete
Physical Progress6%
Planned Progress28%
Time Elapsed30.8%
On Track • 97 days left

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2026-10-07
Completed
Scheduled Completion
2027-02-09
On Track
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceNorth Western Province
DistrictKurunegala
PD RegionNorth Western Province
CE RegionKurunegala
EE Division-
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Kadigawa Bridge Approaches on Pahala Mawathagama - Kadigawa Road (0+000-0+175)
Estimated Road Lengths- km
Number of Roads-
Scope Summary-
Contractor & Award
Contract No.RDA/DRP/NWP/KURU/MAHO/06R
Tender Batch No.15
Contractor NameRCDC Construction Company (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date—
Contract Amount75,025,358.95
Engineer Estimate Amount (LKR)60,148,814.16
Duration (Days)91
CategoryEmergency