DRRRP Awarded Pd

RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/29

Construction of Slope failure mitigation measures along Peradeniya-Badulla-Chenkaladi Road (A005) at Ch 21+550 km

KandyCentral ProvinceGampolaDivisional SecretariatWeebadda ConstructionContractorLKR 28,806,688.50Contract Sum105 daysProject Duration
0%
Complete
Physical Progress0%
Planned Progress0%
Time Elapsed0%
On Track • 0 days left

Project Timeline

LOA
2026-09-14
Completed
Possession
–
Pending
Commencement
–
Pending
Scheduled Completion
–
Pending
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceCentral Province
DistrictKandy
PD RegionCentral Province
CE RegionKandy
EE DivisionGampola
Package No.-
Tender By-
Scope
Contract NameConstruction of Slope failure mitigation measures along Peradeniya-Badulla-Chenkaladi Road (A005) at Ch 21+550 km
Estimated Road Lengths- km
Number of Roads-
Scope Summary-
Contractor & Award
Contract No.RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/29
Tender Batch No.-
Contractor NameWeebadda Construction
Consultant-
Tender StatusAwarded
LOA Date2026-09-14
Contract Amount28,806,688.50
Engineer Estimate Amount (LKR)34,156,473.18
Duration (Days)105
CategoryPD(CP) - Slope