DRRRP Awarded Emergency

RDA/DRP/UVA/BAD/BAD/06

Rehabilitation / Improvement of Baragala Haliela Road (25+525-38+000 - Selected Sections) (AA-016) and Bandarawela Uva Highland Etampitiya Road (5+000-16+100) (B-043)

BadullaUva ProvinceBadullaDivisional SecretariatKanwel Constructions & Civil Engineering (Pvt) LtdContractorLKR 254,882,804.50Contract Sum182 daysProject Duration
57%
Complete
Physical Progress57%
Planned Progress100%
Time Elapsed100%
41 days behind schedule

Project Timeline

LOA
2026-03-12
Completed
Possession
–
Pending
Commencement
2026-03-26
Completed
Scheduled Completion
2026-09-24
Completed
Anticipated Completion Date
2026-09-24
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceUva Province
DistrictBadulla
PD RegionUva Province
CE RegionBadulla
EE DivisionBadulla
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Baragala Haliela Road (25+525-38+000 - Selected Sections) (AA-016) and Bandarawela Uva Highland Etampitiya Road (5+000-16+100) (B-043)
Estimated Road Lengths- km
Number of Roads-
Scope SummaryRetainining structures, Drainage construction
Contractor & Award
Contract No.RDA/DRP/UVA/BAD/BAD/06
Tender Batch No.3
Contractor NameKanwel Constructions & Civil Engineering (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date2026-03-12
Contract Amount254,882,804.50
Engineer Estimate Amount (LKR)302,416,798.70
Duration (Days)182
CategoryEmergency