Rehabilitation / Improvement and Asphalt Overlaying on Mampe Kottawa Road (B267) (0+750 - 3+400) (5+100 - 6+120))

ColomboWestern ProvinceColomboDivisional SecretariatKeangnam Engineering & Construction (Pvt) LtdContractorLKR 94,697,340.01Contract Sum63 daysProject Duration
65%
Complete
Physical Progress65%
Planned Progress100%
Time Elapsed100%
134 days behind schedule

Project Timeline

LOA
2026-04-07
Completed
Possession
–
Pending
Commencement
2026-04-21
Completed
Scheduled Completion
2026-06-23
Completed
Anticipated Completion Date
2026-07-11
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceWestern Province
DistrictColombo
PD RegionWestern Province
CE RegionColombo
EE DivisionColombo
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement and Asphalt Overlaying on Mampe Kottawa Road (B267) (0+750 - 3+400) (5+100 - 6+120))
Estimated Road Lengths- km
Number of Roads-
Scope SummaryAsphalt Overlaying
Contractor & Award
Contract No.RDA/DRP/WP/COL/AVI/04
Tender Batch No.6
Contractor NameKeangnam Engineering & Construction (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date2026-04-07
Contract Amount94,697,340.01
Engineer Estimate Amount (LKR)108,030,624.38
Duration (Days)63
CategoryEmergency