DRRRP Awarded Emergency

RDA/DRP/CEN/KDY/KUN/27

Improvement to Structures on Kandy - Jaffna Road 6+500 - 9+910

KandyCentral ProvinceKundasaleDivisional SecretariatGihan EnterpriseContractorLKR 113,434,139.40Contract Sum119 daysProject Duration
66%
Complete
Physical Progress66%
Planned Progress100%
Time Elapsed100%
8 days behind schedule

Project Timeline

LOA
2026-06-16
Completed
Possession
2026-06-30
Completed
Commencement
2026-06-30
Completed
Scheduled Completion
2026-10-27
Completed
Anticipated Completion Date
–
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceCentral Province
DistrictKandy
PD RegionCentral Province
CE RegionKandy
EE DivisionKundasale
Package No.8
Tender By-
Scope
Contract NameImprovement to Structures on Kandy - Jaffna Road 6+500 - 9+910
Estimated Road Lengths- km
Number of Roads0
Scope SummaryConstruction of Gabion Wall
Contractor & Award
Contract No.RDA/DRP/CEN/KDY/KUN/27
Tender Batch No.12
Contractor NameGihan Enterprise
ConsultantTeam Leader
Tender StatusAwarded
LOA Date2026-06-16
Contract Amount113,434,139.40
Engineer Estimate Amount (LKR)122,896,558.88
Duration (Days)119
CategoryEmergency