Rehabilitation / Improvement of Bulathkohupitiya Dedugala Road, Warakapola Ruwanwella Road, Alawathura- Yatapana - Kotiyakumbura Road and Avissawella - Hatton - Nuwaraeliya Road
KegalleSabaragamuwa ProvinceKegalleDivisional SecretariatSouthern Group Civil Construction (Pvt) LtdContractorLKR 260,537,133.84Contract Sum91 daysProject Duration
Schedule Delay54 daysbehind schedule
54 days behind schedule
Commencement
2026-06-10
Completed
Scheduled Completion
2026-09-11
Completed
Anticipated Completion Date
2026-09-11
Delayed Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceSabaragamuwa Province
DistrictKegalle
PD RegionSabaragamuwa Province
CE RegionKegalle
EE DivisionKegalle
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Bulathkohupitiya Dedugala Road, Warakapola Ruwanwella Road, Alawathura- Yatapana - Kotiyakumbura Road and Avissawella - Hatton - Nuwaraeliya Road
Estimated Road Lengths- km
Number of Roads-
Scope Summary0
Contractor & Award
Contract No.RDA/DRP/SAB/KEG/RUW/28
Tender Batch No.4
Contractor NameSouthern Group Civil Construction (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date2026-03-26
Contract Amount260,537,133.84
Engineer Estimate Amount (LKR)284,539,377.98
Duration (Days)91
CategoryEmergency
Document Readiness
5 of 12 required documents received.
5 Received7 Pending
Contractual5/7
LOA IssuedYes
Agreement SignedYes
Escrow AgreementYes
Performance BondYes
Contract Doc. Received—
Insurance—
Advance BondYes
Technical0/5
Source Approval Request—
Drawings Submitted—
Contractor Staff Details—
Work Programme—
Traffic Mgmt & Safety Plan—
Contract Period Timeline
Scheduled Completion
2026-09-11
Anticipated Completion Date
2026-09-11
Duration Elapsed147 / 91 days
Schedule Status54 Days in Delay
Anticipated Completion Date2026-09-11
Project Completed—
Completed Date—
Mobilization
Planned vs Actual
Physical Progress50% vs 100%
Financial Progress21.7% vs 100%
Progress MonitorCritical Delay
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 20.4% of contract
IPC 1 (Advance)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
PD Certified2026-07-22
LKR 22,472,193.99LKR 26,517,188.91DateAmount (excl. VAT)Amount (incl. VAT)
IPC 2 (Advance)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
PD Certified2026-07-22
LKR 22,472,193.99LKR 26,517,188.91DateAmount (excl. VAT)Amount (incl. VAT)
Advance Summary
Advance BondYes
Advance PaidYes
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 21.7% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
IPC 3 (IPC)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
PD Certified2026-08-07
LKR 5,819,757.92LKR 6,867,314.34DateAmount (excl. VAT)Amount (incl. VAT)
IPC 4 (IPC)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
PD Certified2026-08-03
LKR 3,076,853.61LKR 3,630,687.26DateAmount (excl. VAT)Amount (incl. VAT)
IPC 5 (IPC)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
PD Certified2026-09-18
LKR 696,355.25LKR 821,699.20DateAmount (excl. VAT)Amount (incl. VAT)
IPC 6 (IPC)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
PD Certified2026-09-18
LKR 2,077,327.27LKR 2,451,246.18DateAmount (excl. VAT)Amount (incl. VAT)
IPC 7Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 8Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 9Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 10Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 11Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 12Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 13Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 14Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 15Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 16Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 17Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 18Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 19Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 20Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 21Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 22Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 23Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 24Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 25Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 26Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Revised Contract
contract + approved VOs
No variations recorded
This project has no variation orders yet.
EOTs
0 approved · 0 pending
Days Requested
across 0 EOTs
Approved Days
0 approved EOTs
Revised Finish
planned 2026-09-11
No extensions recorded
This project has no extension-of-time requests yet.
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
Yes - projects.advance_bondBank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
Time
Elapsed - 54 Days in Delay
Overall Progress
Overall
Planned: 100%Behind by 50%
Financial Actual: 56.61 Mn / Planned 260.54 MnBehind 203.93 Mn
Critical Issues-
Kegalle - Kegalle
Rehabilitation / Improvement of Bulathkohupitiya Dedugala Road, Warakapola Ruwanwella Road, Alawathura- Yatapana - Kotiyakumbura Road and Avissawella - Hatton - Nuwaraeliya Road
Project Name:
Project #182 - Contract No. RDA/DRP/SAB/KEG/RUW/28
Physical S-Curve - 2026-11-04 - Generated 2026-11-04 08:54
Contract No. RDA/DRP/SAB/KEG/RUW/28
Physical S-Curve - Planned vs Actual
Today: 2026-11-04 - 50%
Weekly Planned (Physical %)
Presentage
Actual financial
Kegalle - Kegalle
Rehabilitation / Improvement of Bulathkohupitiya Dedugala Road, Warakapola Ruwanwella Road, Alawathura- Yatapana - Kotiyakumbura Road and Avissawella - Hatton - Nuwaraeliya Road
Project Name:
Project #182 - Contract No. RDA/DRP/SAB/KEG/RUW/28
Financial S-Curve - 2026-11-04 - Generated 2026-11-04 08:54
Contract No. RDA/DRP/SAB/KEG/RUW/28
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-11-04 - LKR 56.61 Mn
Weekly Planned (Financial Mn)
Documents & Attachments
0 file(s) - up to 25 MB each
| Title | Category | Uploaded By | Size | Date | Actions |
|---|
| No documents uploaded. |
Completion Forecast
Current pace+15.2% / week
Estimated completion2026-11-21
Weeks to 100%3.3
Based on linear trend of your weekly progress snapshots.
Weekly Digest
Last snapshot2026-11-02
Snapshot value50%
Current progress50%
Change+0%
Project Notes 0
No notes yet. Add the first note to start the conversation.