DRRRP Awarded Emergency

RDA/DRP/SAB/RAT/EMB/09

Rehabilitation / Improvement of Pelmadulla - Embilipitiya - Naonagama Road (47+100 - 50+400)

RatnapuraSabaragamuwa ProvinceRatnapuraDivisional SecretariatAnura ConstructionContractorLKR 269,913,795.48Contract Sum91 daysProject Duration
6%
Complete
Physical Progress6%
Planned Progress100%
Time Elapsed100%
68 days behind schedule

Project Timeline

LOA
2026-05-11
Completed
Possession
–
Pending
Commencement
2026-05-09
Completed
Scheduled Completion
2026-08-28
Completed
Anticipated Completion Date
2026-08-28
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSabaragamuwa Province
DistrictRatnapura
PD RegionSabaragamuwa Province
CE RegionRatnapura
EE DivisionRatnapura
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Pelmadulla - Embilipitiya - Naonagama Road (47+100 - 50+400)
Estimated Road Lengths- km
Number of Roads-
Scope SummaryBinder and Asphalt surfacing
Contractor & Award
Contract No.RDA/DRP/SAB/RAT/EMB/09
Tender Batch No.8
Contractor NameAnura Construction
Consultant-
Tender StatusAwarded
LOA Date2026-05-11
Contract Amount269,913,795.48
Engineer Estimate Amount (LKR)290,570,516.98
Duration (Days)91
CategoryEmergency