DRRRP Awarded Pd

RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/11

Construction of Slope failure mitigation measures along Galaha-Pupuressa-Delpitiya Road (B125) at Ch 5+700 km

KandyCentral ProvinceGampolaDivisional SecretariatJ. Kodithuwakkuarachchi & Sons (Pvt) LtdContractorLKR 17,724,816.00Contract Sum105 daysProject Duration
0%
Complete
Physical Progress0%
Planned Progress0%
Time Elapsed0%
On Track • 0 days left

Project Timeline

LOA
2026-10-26
Completed
Possession
–
Pending
Commencement
–
Pending
Scheduled Completion
–
Pending
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceCentral Province
DistrictKandy
PD RegionCentral Province
CE RegionKandy
EE DivisionGampola
Package No.-
Tender ByPD(CP)
Scope
Contract NameConstruction of Slope failure mitigation measures along Galaha-Pupuressa-Delpitiya Road (B125) at Ch 5+700 km
Estimated Road Lengths- km
Number of Roads-
Scope Summary-
Contractor & Award
Contract No.RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/11
Tender Batch No.-
Contractor NameJ. Kodithuwakkuarachchi & Sons (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date2026-10-26
Contract Amount17,724,816.00
Engineer Estimate Amount (LKR)16,121,754.76
Duration (Days)105
CategoryPD(CP) - Slope