BadullaUva ProvinceBadullaDivisional SecretariatSubasingha Contractors (Pvt) LtdContractorLKR 228,783,135.84Contract Sum182 daysProject Duration
12%
Complete
Physical Progress12%
Planned Progress22.5%
Time Elapsed33.5%
On Track • 121 days left

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2026-09-04
Completed
Scheduled Completion
2027-03-05
On Track
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceUva Province
DistrictBadulla
PD RegionUva Province
CE RegionBadulla
EE DivisionBadulla
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Bandarawela Welimada Road (6+000-20+200) (B-044)
Estimated Road Lengths- km
Number of Roads-
Scope Summary-
Contractor & Award
Contract No.RDA/DRP/UVA/BAD/BAN/15R
Tender Batch No.14
Contractor NameSubasingha Contractors (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date—
Contract Amount228,783,135.84
Engineer Estimate Amount (LKR)237,954,791.68
Duration (Days)182
CategoryEmergency