DRRRP Awarded Emergency

RDA/DRP/CEN/NUE/HAN/57

Rehabilitation / Improvement of Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 )

Nuwara EliyaCentral ProvinceHangurankethaDivisional SecretariatSamindra ConstructionContractorLKR 47,755,538.96Contract Sum91 daysProject Duration
30%
Complete
Physical Progress30%
Planned Progress100%
Time Elapsed100%
7 days behind schedule

Project Timeline

LOA
2026-07-09
Completed
Possession
2026-07-30
Completed
Commencement
2026-07-30
Completed
Scheduled Completion
2026-10-28
Completed
Anticipated Completion Date
–
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceCentral Province
DistrictNuwara Eliya
PD RegionCentral Province
CE RegionNuwara Eliya
EE DivisionHanguranketha
Package No.7
Tender By-
Scope
Contract NameRehabilitation / Improvement of Keerthibandarapura Naranthalawa Road
( B -511 ) ( 0+000 - 4+100 )
Estimated Road Lengths- km
Number of Roads0
Scope SummarySurfacing(Asphalt), Drain,Shoulder,Hard shoulder,Retaning wall Construction
Contractor & Award
Contract No.RDA/DRP/CEN/NUE/HAN/57
Tender Batch No.12
Contractor NameSamindra Construction
ConsultantHanguranketha EE
Tender StatusAwarded
LOA Date2026-07-09
Contract Amount47,755,538.96
Engineer Estimate Amount (LKR)44,694,533.62
Duration (Days)91
CategoryEmergency