DRRRP Awarded Emergency

RDA/DRP/SAB/RAT/EMB/10

Rehabilitation / Improvement of Pelmadulla - Embilipitiya - Nonagama Road (AA018) (50+500 - 53+100) & Embilipitiya - Moraketiya - Kiriibbanara - Uda Mauara Road (B549) (0+000-5+500)

RatnapuraSabaragamuwa ProvinceRatnapuraDivisional SecretariatKanwel Constructions & Civil Engineering (Pvt) LtdContractorLKR 260,776,583.43Contract Sum91 daysProject Duration
23.7%
Complete
Physical Progress23.7%
Planned Progress100%
Time Elapsed100%
85 days behind schedule

Project Timeline

LOA
2026-04-22
Completed
Possession
–
Pending
Commencement
2026-05-10
Completed
Scheduled Completion
2026-08-11
Completed
Anticipated Completion Date
–
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSabaragamuwa Province
DistrictRatnapura
PD RegionSabaragamuwa Province
CE RegionRatnapura
EE DivisionRatnapura
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Pelmadulla - Embilipitiya - Nonagama Road (AA018) (50+500 - 53+100) & Embilipitiya - Moraketiya - Kiriibbanara - Uda Mauara Road (B549) (0+000-5+500)
Estimated Road Lengths- km
Number of Roads-
Scope SummaryAsphalt over laying, RC drain, Hard shoulder
Contractor & Award
Contract No.RDA/DRP/SAB/RAT/EMB/10
Tender Batch No.7
Contractor NameKanwel Constructions & Civil Engineering (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date2026-04-22
Contract Amount260,776,583.43
Engineer Estimate Amount (LKR)271,949,863.68
Duration (Days)91