Rehabilitation / Improvement of Kandy Jaffna (A-009)(17+710 - 46+450), Thalgodapitiya - Yatawatta - Dombawela (B-409) (15+030 - 26+800), Palapathwela - Galewela Road B-346)(0+000 - 8+100) Roads
MataleCentral ProvinceMataleDivisional SecretariatLahiru Construction and Consultants (Pvt) LtdContractorLKR 292,279,354.08Contract Sum182 daysProject Duration
Schedule Delay5 daysbehind schedule
5 days behind schedule
Possession
2026-05-02
Completed
Commencement
2026-05-02
Completed
Scheduled Completion
2026-10-30
Completed
Anticipated Completion Date
–
Delayed Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceCentral Province
DistrictMatale
PD RegionCentral Province
CE RegionMatale
EE DivisionMatale
Package No.2
Tender By-
Scope
Contract NameRehabilitation / Improvement of Kandy Jaffna (A-009)(17+710 - 46+450), Thalgodapitiya - Yatawatta - Dombawela (B-409) (15+030 - 26+800), Palapathwela - Galewela Road B-346)(0+000 - 8+100) Roads
Estimated Road Lengths- km
Number of Roads0
Scope SummaryShoulder and embankment constructions, surface applications, construction of drainage structures and construction of retaining structures
Contractor & Award
Contract No.RDA/DRP/CEN/MTL/MTL/32
Tender Batch No.3
Contractor NameLahiru Construction and Consultants (Pvt) Ltd
ConsultantMatale EE
Tender StatusAwarded
LOA Date2026-03-12
Contract Amount292,279,354.08
Engineer Estimate Amount (LKR)395,635,536.56
Duration (Days)182
CategoryEmergency
Document Readiness
5 of 12 required documents received.
5 Received7 Pending
Contractual5/7
LOA IssuedYes
Agreement SignedYes
Escrow AgreementYes
Performance BondYes
Contract Doc. Received—
Insurance—
Advance BondYes
Technical0/5
Source Approval Request—
Drawings Submitted—
Contractor Staff Details—
Work Programme—
Traffic Mgmt & Safety Plan—
Contract Period Timeline
Scheduled Completion
2026-10-30
Anticipated Completion Date
—
Duration Elapsed186 / 182 days
Schedule Status5 Days in Delay
Anticipated Completion Date—
Project Completed—
Completed Date—
Mobilization
Planned vs Actual
Physical Progress68% vs 100%
Financial Progress26% vs 100%
Progress MonitorCritical Delay
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 21.2% of contract
IPC 1 (Advance)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
Request2026-07-03
LKR 52,461,047.86LKR 61,904,036.47CE Certified2026-07-13
LKR 52,461,047.86LKR 61,904,036.47PD Certified—
LKR 52,461,047.84LKR 61,904,036.46DateAmount (excl. VAT)Amount (incl. VAT)
Advance Summary
Advance BondYes
Advance PaidYes
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 26% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
IPC 2 (IPC)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
Request2026-07-01
LKR 5,250,585.98LKR 6,195,691.46CE Certified2026-07-07
LKR 4,463,153.84LKR 5,266,521.53PD Certified—
LKR 4,444,918.28LKR 5,245,003.57DateAmount (excl. VAT)Amount (incl. VAT)
IPC 3 (IPC)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
Request2026-07-02
LKR 4,667,745.23LKR 5,507,939.37CE Certified2026-09-10
LKR 4,335,114.71LKR 5,115,435.36PD Certified2026-09-24
LKR 4,317,402.29LKR 5,094,534.70DateAmount (excl. VAT)Amount (incl. VAT)
IPC 4 (IPC)Paid
DateAmount
(excl. VAT)Amount
(incl. VAT)
PD Certified2026-10-08
LKR 14,693,549.16LKR 17,338,388.00DateAmount (excl. VAT)Amount (incl. VAT)
IPC 5 (IPC)PD Certified
DateAmount
(excl. VAT)Amount
(incl. VAT)
PD Certified2026-10-28
LKR 14,693,549.16LKR 17,243,721.74DateAmount (excl. VAT)Amount (incl. VAT)
IPC 6Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 7Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 8Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 9Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 10Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 11Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 12Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 13Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 14Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 15Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 16Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 17Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 18Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 19Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 20Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 21Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 22Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 23Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 24Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
IPC 25Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Revised Contract
contract + approved VOs
No variations recorded
This project has no variation orders yet.
EOTs
0 approved · 0 pending
Days Requested
across 0 EOTs
Approved Days
0 approved EOTs
Revised Finish
planned 2026-10-30
No extensions recorded
This project has no extension-of-time requests yet.
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
Yes - projects.advance_bondBank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
Time
Elapsed - 5 Days in Delay
Overall Progress
Overall
Planned: 100%Behind by 32%
Financial Actual: 75.92 Mn / Planned 292.28 MnBehind 216.36 Mn
Critical Issues-
Matale - Matale
Rehabilitation / Improvement of Kandy Jaffna (A-009)(17+710 - 46+450), Thalgodapitiya - Yatawatta - Dombawela (B-409) (15+030 - 26+800), Palapathwela - Galewela Road B-346)(0+000 - 8+100) Roads
Project Name:
Project #32 - Contract No. RDA/DRP/CEN/MTL/MTL/32
Physical S-Curve - 2026-11-04 - Generated 2026-11-04 08:52
Contract No. RDA/DRP/CEN/MTL/MTL/32
Physical S-Curve - Planned vs Actual
Today: 2026-11-04 - 68%
Weekly Planned (Physical %)
Presentage
Actual financial
Matale - Matale
Rehabilitation / Improvement of Kandy Jaffna (A-009)(17+710 - 46+450), Thalgodapitiya - Yatawatta - Dombawela (B-409) (15+030 - 26+800), Palapathwela - Galewela Road B-346)(0+000 - 8+100) Roads
Project Name:
Project #32 - Contract No. RDA/DRP/CEN/MTL/MTL/32
Financial S-Curve - 2026-11-04 - Generated 2026-11-04 08:52
Contract No. RDA/DRP/CEN/MTL/MTL/32
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-11-04 - LKR 75.92 Mn
Weekly Planned (Financial Mn)
Documents & Attachments
0 file(s) - up to 25 MB each
| Title | Category | Uploaded By | Size | Date | Actions |
|---|
| No documents uploaded. |
Completion Forecast
Current pace+2.9% / week
Estimated completion2026-12-17
Weeks to 100%10.9
Based on linear trend of your weekly progress snapshots.
Weekly Digest
Last snapshot2026-10-30
Snapshot value68%
Current progress68%
Change+1%
Project Notes 0
No notes yet. Add the first note to start the conversation.