KegalleSabaragamuwa ProvinceKegalleDivisional SecretariatTudawe Brothers (Pvt) LtdContractorLKR 261,228,130.78Contract Sum91 daysProject Duration
65%
Complete
Physical Progress65%
Planned Progress100%
Time Elapsed100%
91 days behind schedule

Project Timeline

LOA
2026-03-12
Completed
Possession
–
Pending
Commencement
2026-05-07
Completed
Scheduled Completion
2026-08-05
Completed
Anticipated Completion Date
2026-08-06
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSabaragamuwa Province
DistrictKegalle
PD RegionSabaragamuwa Province
CE RegionKegalle
EE DivisionKegalle
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Damaged Locations in Colombo Kandy Road from 56+050-98+950
Estimated Road Lengths- km
Number of Roads-
Scope SummaryRetaining Structures
Contractor & Award
Contract No.RDA/DRP/SAB/KEG/KEG/14
Tender Batch No.1
Contractor NameTudawe Brothers (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date2026-03-12
Contract Amount261,228,130.78
Engineer Estimate Amount (LKR)267,884,733.58
Duration (Days)91