DRRRP Awarded Emergency

RDA/DRP/NCP/ANU/MAR/05R

Rehabilitation / Improvement and Rectification of Flood Damage on Thonigala - Kalawewa - Galewela Road (B423) (14+000-14+085 km) & Rectification of Flood Damage on Madatugama Pubbogama Andiyagala Road (B556) (11+930 -12+250 km)

AnuradhapuraNorth Central ProvinceAnuradhapuraDivisional SecretariatNMST ContractorsContractorLKR 89,094,024.31Contract Sum91 daysProject Duration
12%
Complete
Physical Progress12%
Planned Progress80.3%
Time Elapsed74.7%
On Track • 23 days left

Project Timeline

LOA
2026-08-14
Completed
Possession
–
Pending
Commencement
2026-08-28
Completed
Scheduled Completion
2026-11-27
On Track
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceNorth Central Province
DistrictAnuradhapura
PD RegionNorth Central Province
CE RegionAnuradhapura
EE DivisionAnuradhapura
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement and Rectification of Flood Damage on Thonigala - Kalawewa - Galewela Road (B423) (14+000-14+085 km) & Rectification of Flood Damage on Madatugama Pubbogama Andiyagala Road (B556) (11+930 -12+250 km)
Estimated Road Lengths- km
Number of Roads-
Scope Summary-
Contractor & Award
Contract No.RDA/DRP/NCP/ANU/MAR/05R
Tender Batch No.13
Contractor NameNMST Contractors
Consultant-
Tender StatusAwarded
LOA Date2026-08-14
Contract Amount89,094,024.31
Engineer Estimate Amount (LKR)93,874,634.26
Duration (Days)91
CategoryEmergency