DRRRP Awarded Emergency

RDA/DRP/NCP/POL/POL/09

Rehabilitation / Improvement and Reconstruction of Culvert No. 104/2, Construction of New Drainage At 83km, and Concrete Hard Shoulder at 83 Km on Maradankadawala - Habarana - Thirikkondiyadumadu Road (A-11) (82+110 - 82+860 (B/S)

PolonnaruwaNorth Central ProvincePolonnaruwaDivisional SecretariatAbeywardhana ConstructionContractorLKR 94,457,054.66Contract Sum91 daysProject Duration
56%
Complete
Physical Progress56%
Planned Progress100%
Time Elapsed100%
180 days behind schedule

Project Timeline

LOA
2026-04-22
Completed
Possession
–
Pending
Commencement
2026-06-05
Completed
Scheduled Completion
2026-05-08
Completed
Anticipated Completion Date
2026-05-08
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceNorth Central Province
DistrictPolonnaruwa
PD RegionNorth Central Province
CE RegionPolonnaruwa
EE DivisionPolonnaruwa
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement and Reconstruction of Culvert No. 104/2, Construction of New Drainage At 83km, and Concrete Hard Shoulder at 83 Km on Maradankadawala - Habarana - Thirikkondiyadumadu Road (A-11) (82+110 - 82+860 (B/S)
Estimated Road Lengths- km
Number of Roads-
Scope Summary104/2 Culvert on MHT Reconstruction, Built up Drains & Hard Shoulder Construction
Contractor & Award
Contract No.RDA/DRP/NCP/POL/POL/09
Tender Batch No.7
Contractor NameAbeywardhana Construction
Consultant-
Tender StatusAwarded
LOA Date2026-04-22
Contract Amount94,457,054.66
Engineer Estimate Amount (LKR)119,605,688.26
Duration (Days)91
CategoryEmergency