DRRRP Awarded Emergency

RDA/DRP/UVA/BAD/BAN/19

Rehabilitation / Improvement of Bandarawela Liyangahawela Poonagala Road (5+000 -10+000) (B-042)

BadullaUva ProvinceBadullaDivisional SecretariatSenura Civil Engineering (Pvt) LtdContractorLKR 216,526,489.67Contract Sum120 daysProject Duration
40%
Complete
Physical Progress40%
Planned Progress100%
Time Elapsed100%
42 days behind schedule

Project Timeline

LOA
2026-03-12
Completed
Possession
–
Pending
Commencement
2026-03-26
Completed
Scheduled Completion
2026-09-23
Completed
Anticipated Completion Date
2026-09-23
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceUva Province
DistrictBadulla
PD RegionUva Province
CE RegionBadulla
EE DivisionBadulla
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Bandarawela Liyangahawela Poonagala Road (5+000 -10+000) (B-042)
Estimated Road Lengths- km
Number of Roads-
Scope SummaryAsphalt overlaying and shoulder
Contractor & Award
Contract No.RDA/DRP/UVA/BAD/BAN/19
Tender Batch No.1
Contractor NameSenura Civil Engineering (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date2026-03-12
Contract Amount216,526,489.67
Engineer Estimate Amount (LKR)220,745,970.70
Duration (Days)120
CategoryEmergency