DRRRP Awarded Emergency

RDA/DRP/CEN/KDY/KUN/20

Rehabilitation / Improvement to Structures on Madolkelle - Kabaragala - Kandenuwara Road (B 257) (4+000 - 8+000)

KandyCentral ProvinceKundasaleDivisional SecretariatSamindra ConstructionContractorLKR 31,558,227.98Contract Sum119 daysProject Duration
53%
Complete
Physical Progress53%
Planned Progress93.1%
Time Elapsed89.9%
On Track • 11 days left

Project Timeline

LOA
2026-07-06
Completed
Possession
2026-07-20
Completed
Commencement
2026-07-20
Completed
Scheduled Completion
2026-11-15
On Track
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceCentral Province
DistrictKandy
PD RegionCentral Province
CE RegionKandy
EE DivisionKundasale
Package No.1
Tender By-
Scope
Contract NameRehabilitation / Improvement to Structures on Madolkelle - Kabaragala - Kandenuwara Road (B 257) (4+000 - 8+000)
Estimated Road Lengths- km
Number of Roads0
Scope SummaryConstruction of Retaining wall and Gabion wall
Contractor & Award
Contract No.RDA/DRP/CEN/KDY/KUN/20
Tender Batch No.-
Contractor NameSamindra Construction
ConsultantTeam Leader
Tender StatusAwarded
LOA Date2026-07-06
Contract Amount31,558,227.98
Engineer Estimate Amount (LKR)28,660,618.70
Duration (Days)119
CategoryEmergency