DRRRP Awarded Emergency

RDA/DRP/UVA/BAD/BAN/17R

Rehabilitation / Improvement of Welimada Boralanda Ohiya Horton Plains (0+000 -32+470)(B-508)

BadullaUva ProvinceBadullaDivisional SecretariatShabi Lanka ConstructionContractorLKR 148,910,781.64Contract Sum126 daysProject Duration
7%
Complete
Physical Progress7%
Planned Progress48.8%
Time Elapsed48.4%
On Track • 64 days left

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2026-09-04
Completed
Scheduled Completion
2027-01-07
On Track
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceUva Province
DistrictBadulla
PD RegionUva Province
CE RegionBadulla
EE DivisionBadulla
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Welimada Boralanda Ohiya Horton Plains (0+000 -32+470)(B-508)
Estimated Road Lengths- km
Number of Roads-
Scope Summary-
Contractor & Award
Contract No.RDA/DRP/UVA/BAD/BAN/17R
Tender Batch No.14
Contractor NameShabi Lanka Construction
Consultant-
Tender StatusAwarded
LOA Date—
Contract Amount148,910,781.64
Engineer Estimate Amount (LKR)116,248,771.28
Duration (Days)126
CategoryEmergency