DRRRP Awarded Emergency

RDA/DRP/SAB/RAT/EMB/02

Rehabilitation / Improvement of Pelmadulla - Embilipitiya - Nonagama Road (40+500-43+300)

RatnapuraSabaragamuwa ProvinceRatnapuraDivisional SecretariatAnura ConstructionContractorLKR 260,511,600.34Contract Sum91 daysProject Duration
21%
Complete
Physical Progress21%
Planned Progress100%
Time Elapsed100%
103 days behind schedule

Project Timeline

LOA
2026-04-07
Completed
Possession
–
Pending
Commencement
2026-04-24
Completed
Scheduled Completion
2026-07-24
Completed
Anticipated Completion Date
2026-07-24
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSabaragamuwa Province
DistrictRatnapura
PD RegionSabaragamuwa Province
CE RegionRatnapura
EE DivisionRatnapura
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Pelmadulla - Embilipitiya - Nonagama Road (40+500-43+300)
Estimated Road Lengths- km
Number of Roads-
Scope Summary2.8 km (Wearing+Binder), Culvert Nos 2, Drain Construction
Contractor & Award
Contract No.RDA/DRP/SAB/RAT/EMB/02
Tender Batch No.6
Contractor NameAnura Construction
Consultant-
Tender StatusAwarded
LOA Date2026-04-07
Contract Amount260,511,600.34
Engineer Estimate Amount (LKR)297,894,808.58
Duration (Days)91
CategoryEmergency