DRRRP Awarded Emergency

RDA/DRP/NOR/VOU/VOU/15

Rehabilitation /Improvement of Kandy-Jaffna Road (AA009) & Madawachchiya-Mannar-Thalaimannar Road (AA014)

VavuniyaNorthern ProvinceVavuniyaDivisional SecretariatJana Civil Work Contractors & Material SuppliersContractorLKR 42,832,926.51Contract Sum119 daysProject Duration
18%
Complete
Physical Progress18%
Planned Progress62.5%
Time Elapsed58%
On Track • 49 days left

Project Timeline

LOA
–
Pending
Possession
–
Pending
Commencement
2026-08-27
Completed
Scheduled Completion
2026-12-23
On Track
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceNorthern Province
DistrictVavuniya
PD RegionNorthern Province
CE RegionVavuniya
EE DivisionVavuniya
Package No.-
Tender By-
Scope
Contract NameRehabilitation /Improvement of Kandy-Jaffna Road (AA009) & Madawachchiya-Mannar-Thalaimannar Road (AA014)
Estimated Road Lengths- km
Number of Roads-
Scope Summary-
Contractor & Award
Contract No.RDA/DRP/NOR/VOU/VOU/15
Tender Batch No.13
Contractor NameJana Civil Work Contractors & Material Suppliers
Consultant-
Tender StatusAwarded
LOA Date—
Contract Amount42,832,926.51
Engineer Estimate Amount (LKR)46,307,621.71
Duration (Days)119
CategoryEmergency