DRRRP Awarded Emergency

RDA/DRP/WP/COL/COL/06

Rehabilitation / Improvement of Allen Avenue (B011) (0+000- 2+000)

ColomboWestern ProvinceColomboDivisional SecretariatJayasinghe Construction (Pvt) LtdContractorLKR 144,822,585.09Contract Sum91 daysProject Duration
5%
Complete
Physical Progress5%
Planned Progress100%
Time Elapsed100%
87 days behind schedule

Project Timeline

LOA
2026-04-22
Completed
Possession
–
Pending
Commencement
2026-05-10
Completed
Scheduled Completion
2026-08-09
Completed
Anticipated Completion Date
–
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceWestern Province
DistrictColombo
PD RegionWestern Province
CE RegionColombo
EE DivisionColombo
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Allen Avenue (B011) (0+000- 2+000)
Estimated Road Lengths- km
Number of Roads-
Scope SummaryAsphalt Overlaying
Contractor & Award
Contract No.RDA/DRP/WP/COL/COL/06
Tender Batch No.7
Contractor NameJayasinghe Construction (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date2026-04-22
Contract Amount144,822,585.09
Engineer Estimate Amount (LKR)146,669,652.60
Duration (Days)91
CategoryEmergency