DRRRP Awarded Emergency

RDA/DRP/CEN/NUE/NUR/101

Rehabilitation/Improvement of Hatton Maskeliya Delhouse Road (B-149) (0+000-31+970)

Nuwara EliyaCentral ProvinceNorwoodDivisional SecretariatSooriya BuildersContractorLKR 86,746,198.17Contract Sum147 daysProject Duration
31%
Complete
Physical Progress31%
Planned Progress98.3%
Time Elapsed94.6%
On Track • 7 days left

Project Timeline

LOA
2026-05-19
Completed
Possession
2026-06-18
Completed
Commencement
2026-06-18
Completed
Scheduled Completion
2026-11-11
On Track
Anticipated Completion Date
–
Pending

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceCentral Province
DistrictNuwara Eliya
PD RegionCentral Province
CE RegionNuwara Eliya
EE DivisionNorwood
Package No.15
Tender By-
Scope
Contract NameRehabilitation/Improvement of Hatton Maskeliya Delhouse Road (B-149) (0+000-31+970)
Estimated Road Lengths- km
Number of Roads0
Scope SummaryAsphalt overlay, Road Marking ,Retaining wall Construction,Drain Construction & Culvert Construction.
Contractor & Award
Contract No.RDA/DRP/CEN/NUE/NUR/101
Tender Batch No.10
Contractor NameSooriya Builders
ConsultantNorwood EE
Tender StatusAwarded
LOA Date2026-05-19
Contract Amount86,746,198.17
Engineer Estimate Amount (LKR)108,611,538.67
Duration (Days)147
CategoryEmergency