RDA/DRP/UVA/MON/MON/28
Rehabilitation / Improvement of Colombo Galle Hambanthota Wellawaya Road (305+650-305+850) (AA-002), Wellawaya Ella Kumbalwela Road (0+800-1+825) (AA-023) and Kumbukkana Okkampitiya Maligawila Road (2+250-2+450) (B-513)
MonaragalaUva ProvinceMonaragalaDivisional SecretariatEMA Construction (Pvt) LtdContractorLKR 86,302,421.23Contract Sum180 daysProject Duration
59%
Complete
Physical Progress59%
Planned Progress100%
Time Elapsed100%
Schedule Delay33 daysbehind schedule
33 days behind schedule
Project Timeline
LOA
2026-03-12
CompletedPossession
–
PendingCommencement
2026-04-06
CompletedScheduled Completion
2026-10-02
CompletedAnticipated Completion Date
2026-10-02
DelayedSwipe tabs to see all sections — tap to switch
Location & Package
ProvinceUva Province
DistrictMonaragala
PD RegionUva Province
CE RegionMonaragala
EE DivisionMonaragala
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Colombo Galle Hambanthota Wellawaya Road (305+650-305+850) (AA-002), Wellawaya Ella Kumbalwela Road (0+800-1+825) (AA-023) and Kumbukkana Okkampitiya Maligawila Road (2+250-2+450) (B-513)
Estimated Road Lengths- km
Number of Roads-
Scope SummaryRetaining Structure
Contractor & Award
Contract No.RDA/DRP/UVA/MON/MON/28
Tender Batch No.1
Contractor NameEMA Construction (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date2026-03-12
Contract Amount86,302,421.23
Engineer Estimate Amount (LKR)118,529,679.67
Duration (Days)180
CategoryEmergency
IPC 4Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 5Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 6Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 7Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 8Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 9Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 10Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 11Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 12Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 13Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 14Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 15Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 16Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 17Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 18Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 19Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 20Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 21Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 22Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 23Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
