RDA/DRP/CEN/MTL/MTL/35
Rehabilitation / Improvement of Rattota Gammaduwa Road (7+100 - 11+260)
MataleCentral ProvinceMataleDivisional SecretariatKanwel Constructions & Civil Engineering (Pvt) LtdContractorLKR 266,607,902.15Contract Sum182 daysProject Duration
63%
Complete
Physical Progress63%
Planned Progress100%
Time Elapsed100%
Schedule Delay5 daysbehind schedule
5 days behind schedule
Project Timeline
LOA
2026-03-16
CompletedPossession
–
PendingCommencement
2026-05-02
CompletedScheduled Completion
2026-10-30
CompletedAnticipated Completion Date
–
DelayedSwipe tabs to see all sections — tap to switch
Location & Package
ProvinceCentral Province
DistrictMatale
PD RegionCentral Province
CE RegionMatale
EE DivisionMatale
Package No.5
Tender By-
Scope
Contract NameRehabilitation / Improvement of Rattota Gammaduwa Road (7+100 - 11+260)
Estimated Road Lengths- km
Number of Roads0
Scope SummaryEarth works, base and shoulder work surface application, construction of drainage structures, construction of retaining structures and culvert construction
Contractor & Award
Contract No.RDA/DRP/CEN/MTL/MTL/35
Tender Batch No.4
Contractor NameKanwel Constructions & Civil Engineering (Pvt) Ltd
ConsultantMatale EE
Tender StatusAwarded
LOA Date2026-03-16
Contract Amount266,607,902.15
Engineer Estimate Amount (LKR)291,904,507.83
Duration (Days)182
CategoryEmergency
IPC 4Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 5Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 6Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 7Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 8Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 9Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 10Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 11Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 12Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 13Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 14Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 15Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 16Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 17Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 18Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 19Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 20Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 21Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 22Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount
IPC 23Not Started
DateAmount (excl. VAT)Amount (incl. VAT)
Request
CE Certified
PD Certified
Paid
——Advance Recovered
Retention Amount