DRRRP Awarded Emergency

RDA/DRP/UVA/BAD/BAD/02

Rehabilitation / Improvement of Demodara SpringValley Badulla Road (16+145-20+800) - selected Sections) (B-097)

BadullaUva ProvinceBadullaDivisional SecretariatPriyankara Industries & ContractorsContractorLKR 241,775,532.44Contract Sum180 daysProject Duration
66%
Complete
Physical Progress66%
Planned Progress100%
Time Elapsed100%
43 days behind schedule

Project Timeline

LOA
2026-03-12
Completed
Possession
–
Pending
Commencement
2026-03-26
Completed
Scheduled Completion
2026-09-22
Completed
Anticipated Completion Date
2026-09-22
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceUva Province
DistrictBadulla
PD RegionUva Province
CE RegionBadulla
EE DivisionBadulla
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Demodara SpringValley Badulla Road (16+145-20+800) - selected Sections) (B-097)
Estimated Road Lengths- km
Number of Roads-
Scope SummaryRetaining Structures, Drainage construction
Contractor & Award
Contract No.RDA/DRP/UVA/BAD/BAD/02
Tender Batch No.1
Contractor NamePriyankara Industries & Contractors
Consultant-
Tender StatusAwarded
LOA Date2026-03-12
Contract Amount241,775,532.44
Engineer Estimate Amount (LKR)286,001,165.69
Duration (Days)180
CategoryEmergency