DRRRP Awarded Emergency

RDA/DRP/WP/GAM/NIT/22

Rehabilitation / Improvement of Delgoda Dompe Giridara Road (Selected Sections between 2+000-12+100)

GampahaWestern ProvinceGampahaDivisional SecretariatSenarath Engineering (Pvt) LtdContractorLKR 264,745,054.48Contract Sum182 daysProject Duration
1%
Complete
Physical Progress1%
Planned Progress100%
Time Elapsed100%
12 days behind schedule

Project Timeline

LOA
2026-04-06
Completed
Possession
–
Pending
Commencement
2026-04-24
Completed
Scheduled Completion
2026-10-23
Completed
Anticipated Completion Date
–
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceWestern Province
DistrictGampaha
PD RegionWestern Province
CE RegionGampaha
EE DivisionGampaha
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Delgoda Dompe Giridara Road (Selected Sections between 2+000-12+100)
Estimated Road Lengths- km
Number of Roads-
Scope SummaryAsphalt Overlaying
Contractor & Award
Contract No.RDA/DRP/WP/GAM/NIT/22
Tender Batch No.5
Contractor NameSenarath Engineering (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date2026-04-06
Contract Amount264,745,054.48
Engineer Estimate Amount (LKR)294,920,837.23
Duration (Days)182
CategoryEmergency