DRRRP Awarded Emergency

RDA/DRP/UVA/BAD/BAD/01

Rehabilitation / Improvement of Badulla Karametiya Andaulpotha Road (0+000-20+000 - Selected Sections) (B-036)

BadullaUva ProvinceBadullaDivisional SecretariatJD BuildersContractorLKR 210,946,129.78Contract Sum182 daysProject Duration
71%
Complete
Physical Progress71%
Planned Progress100%
Time Elapsed100%
38 days behind schedule

Project Timeline

LOA
2026-03-16
Completed
Possession
–
Pending
Commencement
2026-03-30
Completed
Scheduled Completion
2026-09-27
Completed
Anticipated Completion Date
2026-09-27
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceUva Province
DistrictBadulla
PD RegionUva Province
CE RegionBadulla
EE DivisionBadulla
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement of Badulla Karametiya Andaulpotha Road (0+000-20+000 - Selected Sections) (B-036)
Estimated Road Lengths- km
Number of Roads-
Scope SummaryRetaining structures
Contractor & Award
Contract No.RDA/DRP/UVA/BAD/BAD/01
Tender Batch No.2
Contractor NameJD Builders
Consultant-
Tender StatusAwarded
LOA Date2026-03-16
Contract Amount210,946,129.78
Engineer Estimate Amount (LKR)292,708,768.01
Duration (Days)182
CategoryEmergency