DRRRP Awarded Emergency

RDA/DRP/SAB/RAT/RAT/22

Rehabilitation / Improvement and Asphalt Overlaying on Ayagama Kukulegama Road

RatnapuraSabaragamuwa ProvinceRatnapuraDivisional SecretariatKeangnam Engineering & Construction (Pvt) LtdContractorLKR 280,145,000.74Contract Sum91 daysProject Duration
42.9%
Complete
Physical Progress42.9%
Planned Progress100%
Time Elapsed100%
131 days behind schedule

Project Timeline

LOA
2026-03-13
Completed
Possession
–
Pending
Commencement
2026-03-27
Completed
Scheduled Completion
2026-06-26
Completed
Anticipated Completion Date
2026-09-25
Delayed

Swipe tabs to see all sections — tap to switch

Location & Package
ProvinceSabaragamuwa Province
DistrictRatnapura
PD RegionSabaragamuwa Province
CE RegionRatnapura
EE DivisionRatnapura
Package No.-
Tender By-
Scope
Contract NameRehabilitation / Improvement and Asphalt Overlaying on Ayagama Kukulegama Road
Estimated Road Lengths- km
Number of Roads-
Scope Summary6 km Asphalt Overlaying, Culvert Construction
Contractor & Award
Contract No.RDA/DRP/SAB/RAT/RAT/22
Tender Batch No.2
Contractor NameKeangnam Engineering & Construction (Pvt) Ltd
Consultant-
Tender StatusAwarded
LOA Date2026-03-13
Contract Amount280,145,000.74
Engineer Estimate Amount (LKR)316,600,518.19
Duration (Days)91
CategoryEmergency