Comprehensive overview of 3 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-04 10:30Live
Graphs reflect current view:3 awarded · Matale · EE: Nalanda

Portfolio Breakdown · Matale · EE: Nalanda · EE Office

10Awarded18Total
Nalanda 3 awarded of 6 Open filtered view
CategoryTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Emergency330100%125.2112.666.720.218% of contract69.5%55.0%
DC - Roads2020%247.60.0————
DC - Slope1010%111.00.0————
PD(CP) - Slope0000%0.00.0————
Nalanda63350%483.8112.666.720.218% of contract69.5%55.0%

Avg Physical Progress per EE Division · Matale · EE: Nalanda

Portfolio Timeline· 3 scheduled projects · Matale · EE: Nalanda Toggle
Portfolio · Awarded Works

Awarded Projects

1 projects

1/1 (filtered)

Filter awarded works

1 matching project1 active

ActiveDelayed only
Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DRP/CEN/MTL/NAL/51
Rehabilitation /Improvement of Retaining wall , drains and shoulder construction Bowathenna Access Road (B-064) (0+000-2+410)
90%
17,458,592.7825,992,198.15Awarded
Showing 1–1 of 1
Per page:
Source: DRRRP • 6 projects • Data updated 2026-11-04 10:30 • 11:42:20