DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 3 awarded projects

2026-11-04
21:42:46Live2026-11-04
0 / 3Advance Pendingpending advance projects / total projects
0 / 3IPC Pendingpending IPC projects / total projects
2 / 3Advance Paidadvance paid projects / total projects
0 / 3IPCs PaidIPC paid projects / total projects
395.9 Mn

395.90 Mn

Total Contract

20.5 Mn

20.50 Mn

Advance Paid (excl. VAT)

0.0 Mn

— Mn

IPCs Paid (excl. VAT)

20.5 Mn

20.50 Mn

Total Paid (excl. VAT)

24.2 Mn

24.19 Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

24.2 Mn

24.19 Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

5.2%

5.2%

Financial Progress (excl. VAT)

Total (Paid+Pend) excl / Contract

Planned

92.7%

Planned Financial Progress

Planned share of contract value

Portfolio Breakdown — Financial (Exclusive Vat) · Ampara · District

171Projects34,005.3Contract Mn
Reset
Ampara 3 projects Open filtered view
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency3395.924.26% of contract—2220.5———94.8%5.2%
DC - Roads00.0——————————
DC - Slope00.0——————————
PD(CP) - Slope00.0——————————
Ampara3395.924.26% of contract0.02220.5000.094.8%5.2%
Emergency3 projects395.9Mn
6% paid24.2 Mn
Pending—
Planned Fin94.8%
Actual Fin5.2%
Advance & IPC
Advance paid2 proj · 20.5 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Roads0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
Ampara3 projects395.9Mn
6% paid24.2 Mn
Pending0.0Mn
Planned Fin94.8%
Actual Fin5.2%

Avg Physical Progress per Province · Ampara

Graphs reflect current view:3 awarded · Ampara
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 92 projects (filtered from 171)

41–50/92 (filtered from 171)

Filter financial register

92 matching projects1 active

ActiveDelayed only
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
41RDA/DRP/SAB/RAT/RAT/24
Rehabilitation / Improvement and Asphalt Overlaying on Kalawana - Deepdeen Rakwa…
SSP Engineers (Pvt) Ltd
236,752,750.5941,882,954.6449,421,886.47——31,108,406.9736,707,920.23——72,991,361.61—
86.13Mn
36.4%
Watch
86.13Mn
36.4%
42RDA/DRP/SAB/KEG/RUW/28
Rehabilitation / Improvement of Bulathkohupitiya Dedugala Road, Warakapola Ruwan…
Southern Group Civil Construction (Pvt) …
260,537,133.8444,944,387.9853,034,377.82——11,670,294.0513,770,946.98——56,614,682.03—
66.81Mn
25.6%
Watch
66.81Mn
25.6%
43RDA/DRP/SAB/KEG/RUW/35
Yatiyanthota - Poonagala - Meenagala Road (from 13+400 to 18+200)
Southern Group Civil Construction (Pvt) …
170,714,785.5430,937,051.9236,305,721.27——4,255,880.155,021,913.58——35,192,932.07—
41.33Mn
24.2%
Watch
41.33Mn
24.2%
44RDA/DPR/NCP/ANU/ANU/02
Rehabilitation / Improvement and Construction of Drainge Canal for Kumbichchan K…
SMA Construction (Pvt) Ltd
138,891,057.6521,646,336.3925,542,676.94——————21,646,336.39—
25.54Mn
18.4%
Behind
25.54Mn
18.4%
45RDA/DPR/NCP/ANU/ANU/03
Rehabilitation / Improvement Construction of Drainge Canal for Thambuttegama Tan…
SMA Construction (Pvt) Ltd
132,437,825.5023,099,490.2027,257,398.44——————23,099,490.20—
27.26Mn
20.6%
Watch
27.26Mn
20.6%
46RDA/DRP/WP/GAM/NEG/19
Rehabilitation / Improvement of Negombo-Mirigama Road (5+000-6+000) and Negombo…
Tudawe Brothers (Pvt) Ltd
206,184,462.5737,452,084.1044,193,459.24——————37,452,084.10—
44.19Mn
21.4%
Watch
44.19Mn
21.4%
47RDA/DRP/WP/GAM/NIT/21
Rehabilitation / Improvement of Hanwella Urapola Road (3+000 - 10+100), Structur…
Tudawe Brothers (Pvt) Ltd
221,768,903.8439,283,558.3146,354,598.81——————39,283,558.31—
46.35Mn
20.9%
Watch
46.35Mn
20.9%
48RDA/DRP/WP/GAM/GAM/10
Rehabilitation / Improvement of Old Minuwangoda Gampaha - Miriswatta Road (9+000…
Senarath Engineering (Pvt) Ltd
92,177,672.5216,747,576.8219,762,140.65——————16,747,576.82—
19.76Mn
21.4%
Watch
19.76Mn
21.4%
49RDA/DRP/WP/GAM/GAM/12
Rehabilitation / Improvement of Acces Road to Peliyagoda interchange (0+000 - 2+…
Senarath Engineering (Pvt) Ltd
151,956,608.9227,570,474.3532,533,159.73——————27,570,474.35—
32.53Mn
21.4%
Watch
32.53Mn
21.4%
50RDA/DRP/WP/GAM/NIT/20
Rehabilitation / Improvement of Bothale Mirigama Road (3+750-4+800), Warakapola …
Jeyanthan Construction
217,881,464.96————————————
Total16,799,029,680.142,276,780,837.162,686,401,372.89——905,188,809.071,068,036,979.0652,935,451.9660,777,795.943,181,969,646.2352,935,451.96
3,754.44Mn
22.3%
3,815.22Mn
22.7%
Showing 41–50 of 92 projects · page 5/10