DRRRP · Sri Lanka

Financial Dashboard

Monitor financial performance across 2 awarded projects

2026-11-04
14:27:12Live2026-11-04
0 / 2Advance Pendingpending advance projects / total projects
0 / 2IPC Pendingpending IPC projects / total projects
2 / 2Advance Paidadvance paid projects / total projects
2 / 2IPCs PaidIPC paid projects / total projects
160.3 Mn

160.34 Mn

Total Contract

28.0 Mn

28.05 Mn

Advance Paid (excl. VAT)

22.1 Mn

22.08 Mn

IPCs Paid (excl. VAT)

50.1 Mn

50.13 Mn

Total Paid (excl. VAT)

59.2 Mn

59.15 Mn

Total Paid (incl. VAT)

0.0 Mn

— Mn

Advance Pend (incl. VAT)

0.0 Mn

— Mn

IPCs Pend (incl. VAT)

59.2 Mn

59.15 Mn

Total (Paid+Pend) (incl. VAT)

Paid incl + Adv Pend incl + IPC Pend incl

31.3%

31.3%

Financial Progress (excl. VAT)

Total (Paid+Pend) excl / Contract

Planned

100%

Planned Financial Progress

Planned share of contract value

Portfolio Breakdown — Financial (Exclusive Vat) · Monaragala · District

171Projects34,005.3Contract Mn
Reset
Monaragala 2 projects Open filtered view
CategoryProjectsContract LKR MnPaid & PendingAdvanceIPCPlanned Fin %Actual Fin %
Paid Mn + %Pending MnAdv ReqAdv PaidAdv Paid MnIPC ReqIPC PaidIPC Paid Mn
Emergency2160.359.237% of contract—2228.04222.1100.0%31.3%
DC - Roads00.0——————————
DC - Slope00.0——————————
PD(CP) - Slope00.0——————————
Monaragala2160.359.237% of contract0.02228.04222.1100.0%31.3%
Emergency2 projects160.3Mn
37% paid59.2 Mn
Pending—
Planned Fin100.0%
Actual Fin31.3%
Advance & IPC
Advance paid2 proj · 28.0 Mn
IPC paid2 proj · 22.1 Mn
Open filtered view
DC - Roads0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
DC - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
PD(CP) - Slope0 projects0.0Mn
0% paid0.0 Mn
Pending—
Planned Fin—
Actual Fin—
Advance & IPC
Advance paid0 proj · 0.0 Mn
IPC paid0 proj · 0.0 Mn
Open filtered view
Monaragala2 projects160.3Mn
37% paid59.2 Mn
Pending0.0Mn
Planned Fin100.0%
Actual Fin31.3%

Avg Physical Progress per Province · Monaragala

Graphs reflect current view:2 awarded · Monaragala
Payments · Expenditure

Financial Summary

Advance payments, IPCs & expenditure per awarded project · 92 projects (filtered from 171)

91–92/92 (filtered from 171)

Filter financial register

92 matching projects1 active

ActiveDelayed only
S/NContract NoContract NameContractorContract
(LKR)
Advance Paid
(excl. VAT)
Advance Paid
(incl. VAT)
Advance Pend
(excl. VAT)
Advance Pend
(incl. VAT)
IPCs Paid
(excl. VAT)
IPCs Paid
(incl. VAT)
IPCs Pend
(excl. VAT)
IPCs Pend
(incl. VAT)
Overall Expenditure
(excl. VAT)
Pending Payments
(excl. VAT)
Financial ProgressFinancial Progress
with Outstanding
91RDA/DRP/NCP/POL/POL/11
Rehabilitation / Improvement and Construction of New Drainage on Polonnaruwa-Tha…
A.D.M Construction
44,474,738.827,582,108.448,946,887.96——————7,582,108.44—
8.95Mn
20.1%
Watch
8.95Mn
20.1%
92RDA/DRP/SP/GAL/HIN/03
Rehabilitation / Improvement of Gabbion Walls along Udugama - Hiniduma (9+920-…
Ceylon Construction Industry Development…
19,453,314.54————————————
Total16,799,029,680.142,276,780,837.162,686,401,372.89——905,188,809.071,068,036,979.0652,935,451.9660,777,795.943,181,969,646.2352,935,451.96
3,754.44Mn
22.3%
3,815.22Mn
22.7%
Showing 91–92 of 92 projects · page 10/10