DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 9 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka. · Team Leader

Updated 2026-11-04 12:46Live
Graphs reflect current view:9 awarded · Team Leader · Nuwara Eliya · EE: Nuwara Eliya
0%

0

Delay

0 / 9 awarded

0%

0

Completed

0 / 9 awarded

Portfolio Breakdown · Team Leader · Nuwara Eliya · EE: Nuwara Eliya · EE Office

10Awarded10Total
Nuwara Eliya 9 awarded of 9 Open filtered view
CategoryTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Emergency220100%543.9498.2180.351.410% of contract52.8%39.5%
DC - Roads660100%3,362.14,137.5——0.0%0.3%
DC - Slope110100%320.0376.6——0.0%0.0%
PD(CP) - Slope0000%0.00.0————
Nuwara Eliya990100%4,226.05,012.3180.351.41% of contract11.7%9.0%

Project-wise Progress · Team Leader · Nuwara Eliya · EE: Nuwara Eliya (9 projects in one graph)

Physical Actual vs Planned per project • Click bar to open project

Clear

Project-wise Physical Progress: Actual vs Planned (%) · Team Leader · Nuwara Eliya · EE: Nuwara Eliya

Average Physical Progress by EE Division · Team Leader · Nuwara Eliya · EE: Nuwara Eliya

Average District-wise Physical Progress (Kandy District)

No district baseline in this view

Try clearing EE / overdue / search filters

At-Risk Projects · Team Leader · Nuwara Eliya · EE: Nuwara Eliya

1
Portfolio Timeline· 3 scheduled projects · Team Leader · Nuwara Eliya · EE: Nuwara Eliya Toggle
Portfolio · Awarded Works

Awarded Projects

9 projects

9/9

Filter awarded works

9 matching projects

Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DRP/CEN/NUE/NUE/60R
Rehabilitation / Improvement of Peradeniya Badulla Chenkaladi Road (A005) (40+750 - 42+850)
10%
336,313,078.73338,287,510.33Awarded
RDA/DRP/CEN/NUE/NUE/66
Rehabilitation / Improvement of Nuwara Eliya Town Road (0+000 - 1+695 ) (0+000 - 0+240 )
69%
161,841,095.70205,630,098.81Awarded
RDA/DC/DRP/CP/NE/NE/04
REHABILITAION/ IMPROVEMENTS OF LADY MACALUMS DRIVE ROAD (2+850 - 5+600KM)
1%
636,338,397.00560,630,000.00Awarded
RDA/DC/DRP/CP/NE/NE/14
Rehabilitation/ Improvement of Lady Macalums Drive (0+000 - 2+700)
0%
711,929,618.35575,100,000.00Awarded
RDA/DC/DRP/CP/NE/NE/05
Rehabilitation/ Improvement of Blackpool Ambewela Pattipola Hortan Plains (5+200 - 12+000)
0%
791,681,996.67612,060,000.00Awarded
RDA/DC/DRP/CP/NE/NE/01
Rehabilitation/ Improvement of Blackpool Ambewela Pattipola Hortan Plains (12+500 - 18+000)
0%
744,680,423.80605,620,000.00Awarded
RDA/DC/DRP/CP/NE/NE/09
Rehabilitation/ Improvement to Blackpool Ambewela Pattipola Hortan Plains ( 19+000 - 23+000)
0%
607,139,242.74487,070,000.00Awarded
RDA/DC/DRP/CP/NE/NE/07
Rehabilitation/ Improvement to Gomburuoya - Balapokuna Road 0+000-8+500Without 5+250-5+450 & 6+900-7+150
0%
645,688,890.82521,587,977.73Awarded
RDA/DC/DRP/SLOPE/CP/NUE/NUE/PACKAGE-31
REHABILITATION OF SELECTED ROADSECTIONS ON PERADENIYA-BADULLA-CHENKALADI ROAD(44TH KM) AND SLOPE FAILURES DUE TO DITWAH CYCLONE
0%
376,649,403.13320,000,000.00Awarded
Showing 1–9 of 9
Per page:
Source: DRRRP • 9 projects • Data updated 2026-11-04 12:46 • 14:29:39