DRRRP · Sri Lanka

Project Monitoring Dashboard

Comprehensive overview of 1 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka. · Team Leader

Updated 2026-11-04 12:13Live
Graphs reflect current view:1 awarded · Team Leader · Central Province · EE: Norwood
0%

0

On Progress

0 / 1 awarded

0%

0

Delay

0 / 1 awarded

0%

0

Critical Delay

0 / 1 awarded

0%

0

Completed

0 / 1 awarded

Portfolio Breakdown · Team Leader · Central Province · EE: Norwood · EE Office

26Awarded26Total
Norwood 1 awarded of 1 Open filtered view
CategoryTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp inclusive-VATPlanned %Actual %
Emergency0000%0.00.0————
DC - Roads0000%0.00.0————
DC - Slope110100%216.0220.3——0.0%0.0%
PD(CP) - Slope0000%0.00.0————
Norwood110100%216.0220.30.00.00% of contract0.0%0.0%

Project-wise Progress · Team Leader · Central Province · EE: Norwood (1 projects in one graph)

Physical Actual vs Planned per project • Click bar to open project

Clear

Project-wise Physical Progress: Actual vs Planned (%) · Team Leader · Central Province · EE: Norwood

Average Physical Progress by EE Division · Team Leader · Central Province · EE: Norwood

Average District-wise Physical Progress (Kandy District)

No district baseline in this view

Try clearing EE / overdue / search filters

At-Risk Projects · Team Leader · Central Province · EE: Norwood

0

No at-risk projects

No open high/critical issues or delayed projects in this view

Portfolio · Awarded Works

Awarded Projects

1 projects

1/1

Filter awarded works

1 matching project

Contract No. Contract Name Progress LOA Amount Estimate Amount Status
RDA/DC/DRP/SLOPE/CP/NUE/NOR/PACKAGE 33
MITIGATION FOR FAILURE LOCATIONS ALONG NORTON MASKELIYA ROAD (B328) (7+020 7+510) AND SLOPE FAILURES DUE TO "DITWAH" CYCLONE -PACKAGE 33
0%
220,338,719.68216,000,000.00Awarded
Showing 1–1 of 1
Per page:
Source: DRRRP • 1 projects • Data updated 2026-11-04 12:13 • 12:42:49