Project Monitoring Dashboard

Comprehensive overview of 6 infrastructure projects under the Disaster Rebuild and Rural Road Project — Sri Lanka.

Updated 2026-11-04 10:30Live
Graphs reflect current view:6 awarded · Puttalam
16.7%

0

On Progress

1 / 6 awarded

0%

0

Delay

0 / 6 awarded

0%

0

Completed

0 / 6 awarded

Portfolio Breakdown · Puttalam · District

171Awarded266Total
Puttalam 6 awarded of 6 Open filtered view
CategoryTotalAwardedPendingAwarded %Estimate LKR MnContract LKR MnPlanned Exp MnActual Exp ex-VATPlanned %Actual %
Emergency660100%1,073.91,098.3787.376.67% of contract75.6%27.3%
DC - Roads0000%0.00.0————
DC - Slope0000%0.00.0————
PD(CP) - Slope0000%0.00.0————
Puttalam660100%1,073.91,098.3787.376.67% of contract75.6%27.3%

Avg Physical Progress per EE Division · Puttalam

Portfolio Timeline· 6 scheduled projects · Puttalam Toggle
Portfolio · Awarded Works

Awarded Projects

0 projects

0/0 (filtered)

Filter awarded works

0 matching projects1 active

ActiveDelay
Showing 0–0 of 0
Per page:
Source: DRRRP • 6 projects • Data updated 2026-11-04 10:30 • 11:37:30