Rehabilitation/Improvement of Hatton Maskeliya Delhouse Road (B-149) (0+000-31+970)
NuwaraEliya - Central Province
Norwood
Sooriya Builders
Timeline
-
147 days - 2026-06-18 -> 2026-11-11
Scheduled Completion
2026-11-11
86,746,198.17 LKR
RDA/DRP/CEN/NUE/NUR/101
— LKR excl. VAT
0% of contract
45 days left
101 / 147 days • 2026-06-18 -> 2026-11-11
Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceCentral Province
DistrictNuwaraEliya
EE DivisionNorwood
Package No.15
Tender By-
Scope
Contract NameRehabilitation/Improvement of Hatton Maskeliya Delhouse Road (B-149) (0+000-31+970)
Estimated Road Lengths- km
Number of Roads0
Scope SummaryAsphalt overlay, Road Marking ,Retaining wall Construction,Drain Construction & Culvert Construction.
Contractor & Award
Contract No.RDA/DRP/CEN/NUE/NUR/101
Tender Batch No.10
Contractor NameSooriya Builders
ConsultantNorwood EE
Tender StatusAwarded
LOA Date2026-05-19
Contract Amount86,746,198.17
Engineer Estimate Amount (LKR)108,611,538.67
Duration (Days)147
CategoryEmergency
Document Readiness
3 of 12 required documents received.
3 Received
9 Pending
Contractual
3/7
LOA Issued
Yes
Agreement Signed
Yes
Escrow Agreement
—
Performance Bond
—
Contract Doc. Received
Yes
Insurance
—
Advance Bond
—
Technical
0/5
Source Approval Request
—
Drawings Submitted
—
Contractor Staff Details
—
Work Programme
—
Traffic Mgmt & Safety Plan
—
Contract Period Timeline
Scheduled Completion
2026-11-11
Duration Elapsed
101 / 147 days
Schedule Status
On schedule - 45 days remaining
Project Completed
—
Completed Date
—
Mobilization
Planned vs Actual
Physical Progress11% vs 77.1%
Financial Progress0% vs 54.1%
Overall Progress
Overall
Planned: 77.1%
Behind by 66.1%
Financial Actual: 0.00 Mn / Planned 46.93 Mn
Behind 46.93 Mn
Critical Issues
-
Progress Breakdown
Structure Construction
0%
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 0% of contract
No Advance IPC yet. Click Add Advance IPC to create IPC 1 as Advance.
0/20 used - next: IPC 1 as Advance
Advance Summary
Advance Bond—
Advance Paid—
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 0% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
No IPC yet. Click Add IPC to create IPC 1 as IPC.
0/20 used - next: IPC 1 as IPC
Revised Contract
contract + approved VOs
Variation Order 1
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 2
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 3
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
- - projects.advance_bond
Bank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
NuwaraEliya - Norwood
Rehabilitation/Improvement of Hatton Maskeliya Delhouse Road (B-149) (0+000-31+970)
Project Name:
Project #101 - Contract No. RDA/DRP/CEN/NUE/NUR/101
Physical S-Curve - 2026-09-27 - Generated 2026-09-27 16:28
Contract No. RDA/DRP/CEN/NUE/NUR/101
Physical S-Curve - Planned vs Actual
Today: 2026-09-27 - 11%
Weekly Planned (Physical %)
Presentage
Actual financial
NuwaraEliya - Norwood
Rehabilitation/Improvement of Hatton Maskeliya Delhouse Road (B-149) (0+000-31+970)
Project Name:
Project #101 - Contract No. RDA/DRP/CEN/NUE/NUR/101
Financial S-Curve - 2026-09-27 - Generated 2026-09-27 16:28
Contract No. RDA/DRP/CEN/NUE/NUR/101
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-09-27 - LKR 0.00 Mn
Weekly Planned (Financial Mn)
Project Timeline
On track
18 Jun 2026
Today - 27 Sep 2026
11 Nov 2026
11% actual
69.2% time elapsed
Documents & Attachments
0 file(s) - up to 25 MB each
| Title |
Category |
Uploaded By |
Size |
Date |
Actions |
| No documents uploaded. |
Completion Forecast
Current pace
+0.6% / week
Estimated completion
2029-07-04
Weeks to 100%
139.2
Based on linear trend of your weekly progress snapshots.
Weekly Digest
Last snapshot
2026-09-25
Snapshot value
11%
Current progress
11%
Change
+1%
Project Notes
0
No notes yet. Add the first note to start the conversation.