Ditwah (CP) Awarded

RDA/DRP/CEN/NUE/NUR/101

Rehabilitation/Improvement of Hatton Maskeliya Delhouse Road (B-149) (0+000-31+970)

NuwaraEliya - Central Province Norwood Sooriya Builders
Progress -66.1% vs plan
11%
Complete
Planned77.1%
Time68.7%
45 days left - 101/147d
Timeline
LOA
2026-05-19
Possession
2026-06-18
Commencement
2026-06-18
Scheduled Completion
2026-11-11
Original Contract

86,746,198.17 LKR

RDA/DRP/CEN/NUE/NUR/101

Total Certified

— LKR excl. VAT

0% of contract

Overall Progress

11%

-66.1% vs planned
Plan 77.1%
Schedule

45 days left

68.7% time

101 / 147 days • 2026-06-18 -> 2026-11-11

Swipe tabs to see all sections — tap to switch

Planned

77.1%

Actual

11%

Presentage

-66.1%

Time Elapsed

68.7%

Days Left

45

Location & Package
ProvinceCentral Province
DistrictNuwaraEliya
EE DivisionNorwood
Package No.15
Tender By-
Scope
Contract NameRehabilitation/Improvement of Hatton Maskeliya Delhouse Road (B-149) (0+000-31+970)
Estimated Road Lengths- km
Number of Roads0
Scope SummaryAsphalt overlay, Road Marking ,Retaining wall Construction,Drain Construction & Culvert Construction.
Contractor & Award
Contract No.RDA/DRP/CEN/NUE/NUR/101
Tender Batch No.10
Contractor NameSooriya Builders
ConsultantNorwood EE
Tender StatusAwarded
LOA Date2026-05-19
Contract Amount86,746,198.17
Engineer Estimate Amount (LKR)108,611,538.67
Duration (Days)147
CategoryEmergency