Progress Ministry Report
Contract status summary for 38 awarded projects in Central Province
38
Awarded Projects
28
In Progress (>0%)
22.2%
Avg Physical Progress
695.81
Total Financial Progress
Progress Ministry Details
38 projects in current view
| # | Tender Batch No | Contract No | District | EE Division | Contractor | Duration (Days) | Start Date | Finish Date | LOA Issued | Agreement | Account Open | Advance Paid | Kick Off | Mobilized | In Progress | Actual Progress % | Fin. Progress (Mn) | Critical Issues |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 3 | RDA/DRP/CEN/KDY/KAD/11 | Kandy | Kadugannawa | Tiasa Construction (Pvt) Ltd | 182 | 2026-03-25 | 2026-09-23 Overdue | Yes | Yes | Yes | Yes | Yes | Yes | Yes |
23%
|
42.62 | — |
| 2 | — | RDA/DRP/CEN/KDY/KAN/14 | Kandy | Kandy | Alucon Industries (Pvt) Ltd | 182 | 2026-09-01 | 2027-03-01 | Yes | — | — | — | Yes | Yes | Yes |
0%
|
0.00 | — |
| 3 | — | RDA/DRP/CEN/KDY/KDY/15 | Kandy | Kandy | Jayawansa Construction (Pvt) Ltd | 182 | 2026-09-09 | 2027-03-09 | Yes | — | — | — | Yes | Yes | Yes |
3.5%
|
0.00 | — |
| 4 | — | RDA/DRP/CEN/KDY/KDY/19 | Kandy | Kandy | Jayawansa Construction (Pvt) Ltd | 182 | 2026-09-17 | 2027-03-18 | Yes | — | — | — | Yes | — | — |
0%
|
0.00 | — |
| 5 | — | RDA/DRP/CEN/KDY/KUN/20 | Kandy | Kundasale | Samindra Construction | 119 | 2026-07-20 | 2026-11-15 | Yes | Yes | — | No | Yes | Yes | Yes |
29%
|
0.00 | — |
| 6 | 4 | RDA/DRP/CEN/KDY/KUN/21 | Kandy | Kundasale | Jayasinghe Construction (Pvt) Ltd | 182 | 2026-04-30 | 2026-10-28 | Yes | Yes | Yes | Yes | Yes | Yes | Yes |
11.5%
|
54.55 | In the process of Termination |
| 7 | 4 | RDA/DRP/CEN/KDY/KUN/22 | Kandy | Kundasale | SD Civil Construction (Pvt) Ltd | 182 | 2026-03-25 | 2026-09-23 Overdue | Yes | Yes | Yes | Yes | Yes | Yes | Yes |
45%
|
47.43 | — |
| 8 | 12 | RDA/DRP/CEN/KDY/KUN/24R | Kandy | Kundasale | Nimsara Constructions & Holdings (Pvt) Ltd | 182 | 2026-09-14 | 2027-03-14 | — | — | — | — | Yes | Yes | Yes |
0.4%
|
0.00 | — |
| 9 | 12 | RDA/DRP/CEN/KDY/KUN/25 | Kandy | Kundasale | S N O Builders (Pvt) Ltd | 119 | 2026-07-06 | 2026-11-01 | Yes | Yes | Yes | Yes | Yes | Yes | Yes |
36%
|
42.68 | NOT YET MOBILIZED |
| 10 | 12 | RDA/DRP/CEN/KDY/KUN/27 | Kandy | Kundasale | Gihan Enterpriese | 119 | 2026-06-30 | 2026-10-27 | Yes | Yes | Yes | Yes | Yes | Yes | Yes |
47%
|
23.75 | NOT YET MOBILIZED |
| 11 | 12 | RDA/DRP/CEN/KDY/KUN/29 | Kandy | Kundasale | S N O Builders (Pvt) Ltd | 182 | 2026-07-06 | 2027-01-03 | Yes | Yes | Yes | Yes | Yes | Yes | Yes |
39%
|
26.08 | NOT YET MOBILIZED |
| 12 | 9 | RDA/DRP/CEN/MTL/MTL/31R | Matale | Matale | Alucon Industries (Pvt) Ltd | 91 | 2026-09-01 | 2026-11-30 | — | — | — | — | Yes | Yes | Yes |
0%
|
0.00 | — |
| 13 | 3 | RDA/DRP/CEN/MTL/MTL/32 | Matale | Matale | Lahiru Construction and Consultants (Pvt) Ltd | 182 | 2026-05-02 | 2026-10-30 | Yes | Yes | Yes | Yes | Yes | Yes | Yes |
64%
|
67.15 | — |
| 14 | 4 | RDA/DRP/CEN/MTL/MTL/33 | Matale | Matale | Jayasinghe Construction (Pvt) Ltd | 91 | 2026-05-02 | 2026-07-31 Overdue | Yes | Yes | Yes | Yes | Yes | Yes | Yes |
25%
|
34.30 | In the process of Termination |
| 15 | 4 | RDA/DRP/CEN/MTL/MTL/35 | Matale | Matale | Kanwel Constructions & Civil Engineering (Pvt) Ltd | 182 | 2026-05-02 | 2026-10-30 | Yes | Yes | Yes | Yes | Yes | Yes | Yes |
59%
|
54.69 | — |
| 16 | 12 | RDA/DRP/CEN/MTL/MTL/38 | Matale | Matale | Ediriweera Construction | 182 | 2026-07-30 | 2027-01-27 | Yes | Yes | Yes | — | Yes | Yes | Yes |
9%
|
0.00 | — |
| 17 | — | RDA/DRP/CEN/MTL/MTL/41 | Matale | Matale | Vikum Construction | 182 | 2026-09-02 | 2027-03-02 | — | — | — | — | Yes | Yes | Yes |
6%
|
0.00 | — |
| 18 | 11 | RDA/DRP/CEN/MTL/NAL/48R | Matale | Nalanda | S A P Engineering (Pvt) Ltd | 154 | — | — | — | — | — | — | — | — | — |
0%
|
0.00 | — |
| 19 | 11 | RDA/DRP/CEN/MTL/NAL/49 | Matale | Nalanda | Platinum Holdings Lanka (Private) Limited | 154 | 2026-06-18 | 2026-11-18 | Yes | Yes | Yes | Yes | Yes | Yes | Yes |
70%
|
14.55 | — |
| 20 | 11 | RDA/DRP/CEN/MTL/NAL/51 | Matale | Nalanda | Platinum Holdings Lanka (Private) Limited | 119 | 2026-06-18 | 2026-10-14 | Yes | Yes | Yes | Yes | Yes | Yes | Yes |
68%
|
5.64 | — |
| 21 | 12 | RDA/DRP/CEN/NUE/HAN/57 | NuwaraEliya | Hanguranketha | Samindra Construction | 91 | 2026-07-30 | 2026-10-28 | Yes | Yes | — | — | Yes | Yes | Yes |
10%
|
0.00 | — |
| 22 | 10 | RDA/DRP/CEN/NUE/NUE/60R | NuwaraEliya | NuwaraEliya | KSJ Construction (Pvt) Ltd | 182 | — | — | — | — | — | — | — | — | — |
0%
|
0.00 | — |
| 23 | 3 | RDA/DRP/CEN/NUE/NUE/66 | NuwaraEliya | NuwaraEliya | KSJ Construction (Pvt) Ltd | 91 | 2026-05-02 | 2026-07-31 Overdue | Yes | Yes | Yes | Yes | Yes | Yes | Yes |
60%
|
51.43 | — |
| 24 | 3 | RDA/DRP/CEN/NUE/NUE/67 | NuwaraEliya | — | KSJ Construction (Pvt) Ltd | 182 | 2026-05-02 | 2026-10-30 | Yes | Yes | Yes | Yes | Yes | Yes | Yes |
70%
|
78.16 | — |
| 25 | 4 | RDA/DRP/CEN/NUE/NUE/68 | NuwaraEliya | NuwaraEliya | Green Scene Construction (Pvt) Ltd | 182 | 2026-05-02 | 2026-10-30 | Yes | Yes | Yes | Yes | Yes | Yes | Yes |
30%
|
45.28 | — |
| 26 | 4 | RDA/DRP/CEN/NUE/NUE/69 | NuwaraEliya | — | Southern group civil construction (Pvt) Ltd | 182 | 2026-05-02 | 2026-10-30 | Yes | Yes | Yes | Yes | Yes | Yes | Yes |
47%
|
90.79 | — |
| 27 | 10 | RDA/DRP/CEN/NUE/NUE/86 | NuwaraEliya | NuwaraEliya | Pragathi Civil Construction | 91 | 2026-06-12 | 2026-09-10 Overdue | Yes | Yes | — | — | Yes | Yes | Yes |
8%
|
0.00 | — |
| 28 | 10 | RDA/DRP/CEN/NUE/NUR/97 | NuwaraEliya | Norwood | Jayawansa Construction (Pvt) Ltd | 91 | 2026-06-17 | 2026-09-15 Overdue | Yes | Yes | Yes | Yes | Yes | Yes | Yes |
40%
|
16.70 | — |
| 29 | 10 | RDA/DRP/CEN/NUE/NUR/98 | NuwaraEliya | Norwood | Pragathi Civil Construction | 182 | 2026-06-18 | 2026-12-16 | Yes | Yes | — | — | Yes | Yes | Yes |
22%
|
0.00 | — |
| 30 | 10 | RDA/DRP/CEN/NUE/NUR/101 | NuwaraEliya | Norwood | Sooriya Builders | 147 | 2026-06-18 | 2026-11-11 | Yes | Yes | — | — | Yes | Yes | Yes |
11%
|
0.00 | — |
| 31 | — | RDA/DC/DRP/CP/NE/NRW/02 | NuwaraEliya | Norwood | U.K.S Lanka Engineering (Pvt) Ltd | 365 | 2026-07-30 | 2027-07-29 | Yes | — | — | — | Yes | Yes | Yes |
3%
|
0.00 | — |
| 32 | — | RDA/DC/DRP/CP/NE/NE/04 | NuwaraEliya | NuwaraEliya | KDA Weerasinghe & Co (Pvt) Ltd | 546 | — | — | Yes | — | — | — | — | — | — |
0%
|
0.00 | — |
| 33 | — | RDA/DC/DRP/SLOPE/CP/KDY/GAMPOLA-09 | Kandy | Gampola | Sanguine Engineering (Pvt) Ltd | 301 | 2026-09-03 | 2027-06-30 | Yes | — | — | — | Yes | Yes | Yes |
2.3%
|
0.00 | — |
| 34 | — | RDA/DC/DRP/CP/NE/NRW/03 | NuwaraEliya | Norwood | Nagma Engineering (Pvt) Ltd | 364 | 2026-09-16 | 2027-09-14 | Yes | — | — | — | Yes | Yes | Yes |
3%
|
0.00 | — |
| 35 | — | RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/01 | Kandy | Gampola | Weebadda Construction | 105 | — | — | — | — | — | — | — | — | — |
0%
|
0.00 | — |
| 36 | — | RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/14 | Kandy | Gampola | Bandaranayake Builders and Construction | 105 | — | — | — | — | — | — | — | — | — |
0%
|
0.00 | — |
| 37 | — | RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/29 | Kandy | Gampola | Weebadda Construction | 105 | — | — | — | — | — | — | — | — | — |
0%
|
0.00 | — |
| 38 | — | RDA/DC/DRP/SLOPE/PD(CP)/KDY/KUN/18,19&20 | Kandy | Kundasale | J. Kodithuwakkuarachchi & Sons (Pvt) Ltd | 105 | — | — | — | — | — | — | — | — | — |
0%
|
0.00 | — |
| No projects match the selected filters. | ||||||||||||||||||
| Total (38) | — | — | — | — | — | 6,567 | — | — | 29 Yes | 22 Yes | 17 Yes | 16 Yes | 31 Yes | 30 Yes | 30 Yes | 22.2% | 695.81 | — |
Tiasa Construction (Pvt) Ltd
Start
2026-03-25
Finish
2026-09-23
LOA
Yes
Agreement Signed
Yes
Account Open
Yes
Advance Paid
Yes
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
42.62
Critical Issues
—
Alucon Industries (Pvt) Ltd
Start
2026-09-01
Finish
2027-03-01
LOA
Yes
Agreement Signed
—
Account Open
—
Advance Paid
—
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
0.00
Critical Issues
—
Jayawansa Construction (Pvt) Ltd
Start
2026-09-09
Finish
2027-03-09
LOA
Yes
Agreement Signed
—
Account Open
—
Advance Paid
—
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
0.00
Critical Issues
—
Jayawansa Construction (Pvt) Ltd
Start
2026-09-17
Finish
2027-03-18
LOA
Yes
Agreement Signed
—
Account Open
—
Advance Paid
—
Kick Off
Yes
Mobilized
—
In Progress
—
Actual Progress
Financial (Mn)
0.00
Critical Issues
—
Samindra Construction
Start
2026-07-20
Finish
2026-11-15
LOA
Yes
Agreement Signed
Yes
Account Open
—
Advance Paid
—
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
0.00
Critical Issues
—
Jayasinghe Construction (Pvt) Ltd
Start
2026-04-30
Finish
2026-10-28
LOA
Yes
Agreement Signed
Yes
Account Open
Yes
Advance Paid
Yes
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
54.55
Critical Issues
In the process of Termination
SD Civil Construction (Pvt) Ltd
Start
2026-03-25
Finish
2026-09-23
LOA
Yes
Agreement Signed
Yes
Account Open
Yes
Advance Paid
Yes
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
47.43
Critical Issues
—
Nimsara Constructions & Holdings (Pvt) Ltd
Start
2026-09-14
Finish
2027-03-14
LOA
—
Agreement Signed
—
Account Open
—
Advance Paid
—
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
0.00
Critical Issues
—
S N O Builders (Pvt) Ltd
Start
2026-07-06
Finish
2026-11-01
LOA
Yes
Agreement Signed
Yes
Account Open
Yes
Advance Paid
Yes
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
42.68
Critical Issues
NOT YET MOBILIZED
Gihan Enterpriese
Start
2026-06-30
Finish
2026-10-27
LOA
Yes
Agreement Signed
Yes
Account Open
Yes
Advance Paid
Yes
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
23.75
Critical Issues
NOT YET MOBILIZED
S N O Builders (Pvt) Ltd
Start
2026-07-06
Finish
2027-01-03
LOA
Yes
Agreement Signed
Yes
Account Open
Yes
Advance Paid
Yes
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
26.08
Critical Issues
NOT YET MOBILIZED
Alucon Industries (Pvt) Ltd
Start
2026-09-01
Finish
2026-11-30
LOA
—
Agreement Signed
—
Account Open
—
Advance Paid
—
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
0.00
Critical Issues
—
Lahiru Construction and Consultants (Pvt) Ltd
Start
2026-05-02
Finish
2026-10-30
LOA
Yes
Agreement Signed
Yes
Account Open
Yes
Advance Paid
Yes
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
67.15
Critical Issues
—
Jayasinghe Construction (Pvt) Ltd
Start
2026-05-02
Finish
2026-07-31
LOA
Yes
Agreement Signed
Yes
Account Open
Yes
Advance Paid
Yes
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
34.30
Critical Issues
In the process of Termination
Kanwel Constructions & Civil Engineering (Pvt) Ltd
Start
2026-05-02
Finish
2026-10-30
LOA
Yes
Agreement Signed
Yes
Account Open
Yes
Advance Paid
Yes
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
54.69
Critical Issues
—
Ediriweera Construction
Start
2026-07-30
Finish
2027-01-27
LOA
Yes
Agreement Signed
Yes
Account Open
Yes
Advance Paid
—
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
0.00
Critical Issues
—
Vikum Construction
Start
2026-09-02
Finish
2027-03-02
LOA
—
Agreement Signed
—
Account Open
—
Advance Paid
—
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
0.00
Critical Issues
—
S A P Engineering (Pvt) Ltd
Start
—
Finish
—
LOA
—
Agreement Signed
—
Account Open
—
Advance Paid
—
Kick Off
—
Mobilized
—
In Progress
—
Actual Progress
Financial (Mn)
0.00
Critical Issues
—
Platinum Holdings Lanka (Private) Limited
Start
2026-06-18
Finish
2026-11-18
LOA
Yes
Agreement Signed
Yes
Account Open
Yes
Advance Paid
Yes
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
14.55
Critical Issues
—
Platinum Holdings Lanka (Private) Limited
Start
2026-06-18
Finish
2026-10-14
LOA
Yes
Agreement Signed
Yes
Account Open
Yes
Advance Paid
Yes
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
5.64
Critical Issues
—
Samindra Construction
Start
2026-07-30
Finish
2026-10-28
LOA
Yes
Agreement Signed
Yes
Account Open
—
Advance Paid
—
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
0.00
Critical Issues
—
KSJ Construction (Pvt) Ltd
Start
—
Finish
—
LOA
—
Agreement Signed
—
Account Open
—
Advance Paid
—
Kick Off
—
Mobilized
—
In Progress
—
Actual Progress
Financial (Mn)
0.00
Critical Issues
—
KSJ Construction (Pvt) Ltd
Start
2026-05-02
Finish
2026-07-31
LOA
Yes
Agreement Signed
Yes
Account Open
Yes
Advance Paid
Yes
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
51.43
Critical Issues
—
KSJ Construction (Pvt) Ltd
Start
2026-05-02
Finish
2026-10-30
LOA
Yes
Agreement Signed
Yes
Account Open
Yes
Advance Paid
Yes
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
78.16
Critical Issues
—
Green Scene Construction (Pvt) Ltd
Start
2026-05-02
Finish
2026-10-30
LOA
Yes
Agreement Signed
Yes
Account Open
Yes
Advance Paid
Yes
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
45.28
Critical Issues
—
Southern group civil construction (Pvt) Ltd
Start
2026-05-02
Finish
2026-10-30
LOA
Yes
Agreement Signed
Yes
Account Open
Yes
Advance Paid
Yes
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
90.79
Critical Issues
—
Pragathi Civil Construction
Start
2026-06-12
Finish
2026-09-10
LOA
Yes
Agreement Signed
Yes
Account Open
—
Advance Paid
—
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
0.00
Critical Issues
—
Jayawansa Construction (Pvt) Ltd
Start
2026-06-17
Finish
2026-09-15
LOA
Yes
Agreement Signed
Yes
Account Open
Yes
Advance Paid
Yes
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
16.70
Critical Issues
—
Pragathi Civil Construction
Start
2026-06-18
Finish
2026-12-16
LOA
Yes
Agreement Signed
Yes
Account Open
—
Advance Paid
—
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
0.00
Critical Issues
—
Sooriya Builders
Start
2026-06-18
Finish
2026-11-11
LOA
Yes
Agreement Signed
Yes
Account Open
—
Advance Paid
—
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
0.00
Critical Issues
—
U.K.S Lanka Engineering (Pvt) Ltd
Start
2026-07-30
Finish
2027-07-29
LOA
Yes
Agreement Signed
—
Account Open
—
Advance Paid
—
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
0.00
Critical Issues
—
KDA Weerasinghe & Co (Pvt) Ltd
Start
—
Finish
—
LOA
Yes
Agreement Signed
—
Account Open
—
Advance Paid
—
Kick Off
—
Mobilized
—
In Progress
—
Actual Progress
Financial (Mn)
0.00
Critical Issues
—
Sanguine Engineering (Pvt) Ltd
Start
2026-09-03
Finish
2027-06-30
LOA
Yes
Agreement Signed
—
Account Open
—
Advance Paid
—
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
0.00
Critical Issues
—
Nagma Engineering (Pvt) Ltd
Start
2026-09-16
Finish
2027-09-14
LOA
Yes
Agreement Signed
—
Account Open
—
Advance Paid
—
Kick Off
Yes
Mobilized
Yes
In Progress
Yes
Actual Progress
Financial (Mn)
0.00
Critical Issues
—
Weebadda Construction
Start
—
Finish
—
LOA
—
Agreement Signed
—
Account Open
—
Advance Paid
—
Kick Off
—
Mobilized
—
In Progress
—
Actual Progress
Financial (Mn)
0.00
Critical Issues
—
Bandaranayake Builders and Construction
Start
—
Finish
—
LOA
—
Agreement Signed
—
Account Open
—
Advance Paid
—
Kick Off
—
Mobilized
—
In Progress
—
Actual Progress
Financial (Mn)
0.00
Critical Issues
—
Weebadda Construction
Start
—
Finish
—
LOA
—
Agreement Signed
—
Account Open
—
Advance Paid
—
Kick Off
—
Mobilized
—
In Progress
—
Actual Progress
Financial (Mn)
0.00
Critical Issues
—
J. Kodithuwakkuarachchi & Sons (Pvt) Ltd
Start
—
Finish
—
LOA
—
Agreement Signed
—
Account Open
—
Advance Paid
—
Kick Off
—
Mobilized
—
In Progress
—
Actual Progress
Financial (Mn)
0.00
Critical Issues
—
Totals (38 projects)
Duration
6,567
Avg Progress
22.2%
Financial
695.81