Rehabilitation / Improvement of Rattota Gammaduwa Road (7+100 - 11+260)
Matale - Central Province
Matale
Kanwel Constructions & Civil Engineering (Pvt) Ltd
Timeline
-
182 days - 2026-05-02 -> 2026-10-30
Scheduled Completion
2026-10-30
266,607,902.15 LKR
RDA/DRP/CEN/MTL/MTL/35
46,351,528.36 LKR excl. VAT
17.4% of contract
33 days left
148 / 182 days • 2026-05-02 -> 2026-10-30
Swipe tabs to see all sections — tap to switch
Project Information
Documents Status
Mobilization & Contract Period
Progress
Advance Payments
IPCs
Variation Order
Advance Bond
Performance Bond
Physical S-Curve
Financial S-Curve
Timeline
Documents
Notes
Location & Package
Province Central Province
District Matale
EE Division Matale
Package No. 5
Tender By RM&M
Province — Central Province Western Province Southern Province Uva Province Sabaragamuwa Province North Western Province North Central Province Northern Province Eastern Province Eastern Province (Akkaraipattu)
District — Kandy Matale NuwaraEliya Colombo Gampaha Kalutara Galle Matara Hambantota Badulla Monaragala Rathnapura Kegalle Kurunegala Chillaw Anuradhapura Polonanaruwa Vavuniya Jaffna Mullaitivu Batticaloa Trincomalee Ampara Akkaraipattu
EE Division — Kandy Kundasale Kadugannawa Gampola Matale Nalanda Nuwara Eliya Norwood Hanguranketha Colombo Avissawella Gampaha Negombo Nittambuwa Kalutara Agalawatta Horana Galle Hiniduma Matara Deniyaya Hambantota Tangalle Badulla Bandarawela Monaragala Bibile Rathnapura Pelmadulla Embilipitiya Kegalle Ruwanwella Kurunegala Kuliyapitiya Maho Chillaw Puttlam Anuradhapura Medawachchiya Maradankadawala Polonanaruwa Habarana Vavuniya Mannar Jaffna Point Pedro Mullaitivu Kilinochchi Batticaloa Trincomalee Ampara Dehiaattakandiya Akkaraipattu Kalmunai
Package No.
Tender By - RM&M DC PD(CP)
Scope
Contract Name Rehabilitation / Improvement of Rattota Gammaduwa Road (7+100 - 11+260)
Estimated Road Lengths - km
Number of Roads 0
Scope Summary Earth works, base and shoulder work surface application, construction of drainage structures, construction of retaining structures and culvert construction
Contractor & Award
Contract No. RDA/DRP/CEN/MTL/MTL/35
Tender Batch No. 4
Contractor Name Kanwel Constructions & Civil Engineering (Pvt) Ltd
Consultant Matale EE
Tender Status Awarded
LOA Date 2026-03-16
Contract Amount 266,607,902.15
Engineer Estimate Amount (LKR) 291,904,507.83
Duration (Days) 182
Category Emergency
Document Readiness
5 of 12 required documents received.
5 Received
7 Pending
Contractual
5/7
LOA Issued
Yes
Agreement Signed
Yes
Escrow Agreement
Yes
Performance Bond
Yes
Contract Doc. Received
—
Insurance
—
Advance Bond
Yes
LOA Issued - Yes No
Agreement Signed - Yes No
Escrow Agreement - Yes No
Performance Bond - Yes No
Contract Doc. Received - Yes No
Insurance - Yes No
Advance Bond - Yes No
Technical
0/5
Source Approval Request
—
Drawings Submitted
—
Contractor Staff Details
—
Work Programme
—
Traffic Mgmt & Safety Plan
—
Source Approval Request - Yes No
Drawings Submitted - Yes No
Contractor Staff Details - Yes No
Work Programme - Yes No
Traffic Mgmt & Safety Plan - Yes No
Contract Period Timeline
Scheduled Completion
2026-10-30
Duration Elapsed
148 / 182 days
Schedule Status
On schedule - 33 days remaining
Project Completed
—
Completed Date
—
Mobilization
Kick Off - Yes No
Mobilized to Site - Yes No
In Progress - Yes No
Planned vs Actual
Physical Progress 59% vs 86.4%
Financial Progress 17.4% vs 72.8%
Overall Progress
Overall
Planned: 86.4%
Behind by 27.4%
Financial Actual: 46.35 Mn / Planned 194.09 Mn
Behind 147.74 Mn
Critical Issues
-
Progress Breakdown
Structure Construction
15%
Drainage Construction
27%
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 20.5% of contract
IPC 1 (Advance)
Paid
Swipe to see all certificate stages
IPC 2 (Advance)
Paid
Swipe to see all certificate stages
Add Advance IPC
2/20 used - next: IPC 3 as Advance
Advance Summary
Advance Bond Yes
Advance Paid Yes
Advance Bond - Yes No
Advance Paid - Yes No
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 17.4% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
No IPC yet. Click Add IPC to create IPC 3 as IPC.
Add IPC
2/20 used - next: IPC 3 as IPC
Revised Contract
contract + approved VOs
Variation Order 1
Not raised
Reason -
Amount LKR 0.00
Prior Approval Send —
Approved —
Reason
Amount
Prior Approval Send - Yes No
Approved - Yes No
Variation Order 2
Not raised
Reason -
Amount LKR 0.00
Prior Approval Send —
Approved —
Reason
Amount
Prior Approval Send - Yes No
Approved - Yes No
Variation Order 3
Not raised
Reason -
Amount LKR 0.00
Prior Approval Send —
Approved —
Reason
Amount
Prior Approval Send - Yes No
Approved - Yes No
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
Yes - projects.advance_bond
Bank -
Security Number -
Amount (Rs.) -
Bond Management By -
Issued Date —
Expire Date —
Extended —
Effective Expire - (released or not set)
Released No
Remarks -
Login with full edit rights to manage this bond.
Presentage
Actual physical
Chart JPG
Table PNG
Full Report PNG
Matale - Matale
Rehabilitation / Improvement of Rattota Gammaduwa Road (7+100 - 11+260)
Project Name:
Project #35 - Contract No. RDA/DRP/CEN/MTL/MTL/35
Physical S-Curve - 2026-09-27 - Generated 2026-09-27 16:25
Contract No. RDA/DRP/CEN/MTL/MTL/35
Physical S-Curve - Planned vs Actual
Today: 2026-09-27 - 59%
Weekly Planned (Physical %)
Presentage
Actual financial
Chart JPG
Table PNG
Full Report PNG
Matale - Matale
Rehabilitation / Improvement of Rattota Gammaduwa Road (7+100 - 11+260)
Project Name:
Project #35 - Contract No. RDA/DRP/CEN/MTL/MTL/35
Financial S-Curve - 2026-09-27 - Generated 2026-09-27 16:25
Contract No. RDA/DRP/CEN/MTL/MTL/35
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-09-27 - LKR 46.35 Mn
Weekly Planned (Financial Mn)
Project Timeline
On track
02 May 2026
Today - 27 Sep 2026
30 Oct 2026
59% actual
81.8% time elapsed
Documents & Attachments
0 file(s) - up to 25 MB each
Title
Category
Uploaded By
Size
Date
Actions
No documents uploaded.
Completion Forecast
Current pace
+3.2% / week
Estimated completion
2026-12-11
Weeks to 100%
12.9
Based on linear trend of your weekly progress snapshots.
Weekly Digest
Last snapshot
2026-09-25
Snapshot value
59%
Current progress
59%
Change
+1%