Ditwah (CP)

Weekly Physical Progress

Track weekly physical progress for 38 awarded projects — planned vs actual by Friday.

2026-09-27
16:22:50Live 2026-09-27

38

Awarded Projects

22.2%

Average Progress

0

Completed

Quick Fill — Physical Progress

Upcoming: 2026-10-02
RDA/DRP/CEN/KDY/KAD/11

Rehabilitation / Improvement of Nawalapitiya - Dolosbage Road ( B -318) ( 10+500 - 19+350 ), Dedugala Dolosbage Road ( B -588) ( 10+100 - 12+410 )

2026-09-25

23.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/KDY/KAN/14

Rehabilitation /Improvement of Katugasthota Medawala road ( B 0206)( 0 + 000 - 9+370)

2026-09-25

0.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/KDY/KDY/15

Rehabilitation / Improvement of Galagedara Rambukkana ( B 122) ( 0+000 - 18+000)

2026-09-25

3.5% 🔒

Locked

2026-10-02

RDA/DRP/CEN/KDY/KDY/19

Rehabilitation / Improvement of Poojapitiya Alawathugoda road ( B 377) ( 0+000 - 8+000)

2026-09-25

0.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/KDY/KUN/20

Rehabilitation / Improvement to Structures on Madolkelle - Kabaragala - Kandenuwara Road (B 257) (4+000 - 8+000)

2026-09-25

29.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/KDY/KUN/21

Improvement of Pitiyegedara-Waththegama-Iriyagasthenna Road (0+000-5+400)

2026-09-25

11.5% 🔒

Locked

2026-10-02

RDA/DRP/CEN/KDY/KUN/22

Improvement to Damaged Road Section on Weeragantota - Randenigala Road. (From CH 19+000 To CH 27+200)

2026-09-25

45.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/KDY/KUN/24R

Rehabilitation / Improvement of Flood damage on Katugastota - Madawala - Bamberella Road (B205) (0-000 - 7+200 and 13+000 - 13+045)

2026-09-25

0.4% 🔒

Locked

2026-10-02

RDA/DRP/CEN/KDY/KUN/25

Construction of Gabion Retaining Wall on Katugastota Madawala Bamberella Road(LHS 9+600 - 9+655), (15+450 - 15+500), (10+235 - 10+300) and Wattegama Matale road (0+400 - 0+435)

2026-09-25

36.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/KDY/KUN/27

Improvement to Structures on Kandy - Jaffna Road 6+500 - 9+910

2026-09-25

47.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/KDY/KUN/29

Improvement to Structures on Kandy - Mahiyanganaya - Padiyaththalawa Road (24+000-71+500) and Moragahamula victoria damtop

2026-09-25

39.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/MTL/MTL/31R

Rehabilitation / Improvement of Matale - Udupihilla Road (AB026) (0+000 - 6+000)

2026-09-25

0.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/MTL/MTL/32

Rehabilitation / Improvement of Kandy Jaffna (A-009)(17+710 - 46+450), Thalgodapitiya - Yatawatta - Dombawela (B-409) (15+030 - 26+800), Palapathwela - Galewela Road B-346)(0+000 - 8+100) Roads

2026-09-25

64.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/MTL/MTL/33

Rehabilitation / Improvement of Wattegama Matale Road (5+280 - 13+160) and Ukuwela Railway station (0+000 - 0+190)

2026-09-25

25.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/MTL/MTL/35

Rehabilitation / Improvement of Rattota Gammaduwa Road (7+100 - 11+260)

2026-09-25

59.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/MTL/MTL/38

Rehabilitation / Improvement of Kalalpitiya Ukuwela Elkaduwa Road (B 180) (0+000 - 13+470)

2026-09-25

9.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/MTL/MTL/41

Rehabilitation / Improvement of Matale Illukkumbura Laggala Road (B 274) (4+000 - 18+000)

2026-09-25

6.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/MTL/NAL/48R

Rehabilitation/Improvement of surfacing (ASphalt) hard shoulder,Shoulder, drain construction at Beligamuwa - Hebarawa- Wilgamuwa Road (B-577) (6+260 -11+950)

—

—

2026-09-27

RDA/DRP/CEN/MTL/NAL/49

Rehabilitation /Improvement of Drains,Hard shoulder & Cash barrier at Naula- Elahera- Pallegama- Hettipola Road (B-312) (8+200-61+240)

2026-09-25

70.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/MTL/NAL/51

Rehabilitation /Improvement of Retaining wall , drains and shoulder construction Bowathenna Access Road (B-064) (0+000-2+410)

2026-09-25

68.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/NUE/HAN/57

Rehabilitation / Improvement of Keerthibandarapura Naranthalawa Road ( B -511 ) ( 0+000 - 4+100 )

2026-09-25

10.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/NUE/NUE/60R

Rehabilitation / Improvement of Peradeniya Badulla Chenkaladi Road (A005) (40+750 - 42+850)

—

—

2026-09-27

RDA/DRP/CEN/NUE/NUE/66

Rehabilitation / Improvement of Nuwara Eliya Town Road (0+000 - 1+695 ) (0+000 - 0+240 )

2026-09-25

60.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/NUE/NUE/67

Rehabilitation / Improvement of Harangala - Kalapitiya - Kumbaloluwa Road (10+480 km - 17+140 km)

2026-09-25

70.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/NUE/NUE/68

Rehabilitation / Improvement of Thawalanthenna Thalawakelle Road (0+000 - 8+000) & (10+000 - 33+200)

2026-09-25

30.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/NUE/NUE/69

Rehabilitation / Improvement of Ulapane Pussallawa Road (6+440 - 15+950)

2026-09-25

47.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/NUE/NUE/86

Rehabilitation / Improvement of Approch road to R'way station (Watagoda/ Thalawakele) Road

2026-09-25

8.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/NUE/NUR/97

Rehabilitation/Improvement of Nawalapitiya Ginigathena Road (B-319)(7+200-12+200)

2026-09-25

40.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/NUE/NUR/98

Rehabilitation/Improvement Harangala Kalapitiya Road (B-148) (0+000-10+700), Approach Road to Hrangala Dam Crest Road (B-491) (0+000-3+820), Nawalapitiya Harangala Road (B-306) (0+000-10+700)

2026-09-25

22.0% 🔒

Locked

2026-10-02

RDA/DRP/CEN/NUE/NUR/101

Rehabilitation/Improvement of Hatton Maskeliya Delhouse Road (B-149) (0+000-31+970)

2026-09-25

11.0% 🔒

Locked

2026-10-02

RDA/DC/DRP/CP/NE/NRW/02

REHABILITATION/ IMPROVEMENT OF APPROCH ROAD TO LAXAPANA POWER HOUSE ROAD CH 6+100 - 12+000

2026-09-25

3.0% 🔒

Locked

2026-10-02

RDA/DC/DRP/CP/NE/NE/04

REHABILITAION/ IMPROVEMENTS OF LADY MACALUMS DRIVE ROAD (2+850 - 5+600KM)

—

—

2026-09-27

RDA/DC/DRP/SLOPE/CP/KDY/GAMPOLA-09

MITIGATION OF FAILURES ALONG RDA ROADS DUE TO CYCLONE DITWAH GAMPOLA NAWALAPITIYA ROAD (AB013) CHAINAGE 10+350 KM

2026-09-25

2.3% 🔒

Locked

2026-10-02

RDA/DC/DRP/CP/NE/NRW/03

REHABILITATION/ IMPROVEMENT TO ROZELLA RAILWAY STATION ROAD (0+000 - 3+300) KM AND WATAWALA RAILWAY STATION ROAD (0+000 - 1+850) KM

2026-09-25

3.0% 🔒

Locked

2026-10-02

RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/01

Construction of Slope failure mitigation measures along Peradeniya-Badulla-Chenkaladi Road (A005) at Ch 0+030 km

—

—

2026-09-27

RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/14

Construction of Slope failure mitigation measures along Atabage-Ulapane Road (B 490) at Ch 4+000 km

—

—

2026-09-27

RDA/DC/DRP/SLOPE/PD(CP)/KDY/GPL/29

Construction of Slope failure mitigation measures along Peradeniya-Badulla-Chenkaladi Road (A005) at Ch 21+550 km

—

—

2026-09-27

RDA/DC/DRP/SLOPE/PD(CP)/KDY/KUN/18,19&20

Construction of Slope failure mitigation measures along Kandy – Mahiyangana – Padiyatalawa Road (A026) at Culvert No 47/5 Culvert No47/10, Culvert No 50/6-51+200 km and Culvert No 52/3-Culvert No 52/5

—

—

2026-09-27