Rehabilitation / Improvement of Wattegama Matale Road (5+280 - 13+160) and Ukuwela Railway station (0+000 - 0+190)
Matale - Central Province
Matale
Jayasinghe Construction (Pvt) Ltd
Timeline
-
91 days - 2026-05-02 -> 2026-07-31
Overdue 58d
Scheduled Completion
2026-07-31
165,006,430.79 LKR
RDA/DRP/CEN/MTL/MTL/33
29,068,239.71 LKR excl. VAT
17.6% of contract
58d overdue
148 / 91 days • 2026-05-02 -> 2026-07-31
Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceCentral Province
DistrictMatale
EE DivisionMatale
Package No.3
Tender ByRM&M
Scope
Contract NameRehabilitation / Improvement of Wattegama Matale Road (5+280 - 13+160) and Ukuwela Railway station (0+000 - 0+190)
Estimated Road Lengths- km
Number of Roads0
Scope SummaryShoulder and embankment construction, surface application, construction of drainage structures and construction of retaining walls
Contractor & Award
Contract No.RDA/DRP/CEN/MTL/MTL/33
Tender Batch No.4
Contractor NameJayasinghe Construction (Pvt) Ltd
ConsultantMatale EE
Tender StatusAwarded
LOA Date2026-03-16
Contract Amount165,006,430.79
Engineer Estimate Amount (LKR)188,777,407.11
Duration (Days)91
CategoryEmergency
Document Readiness
5 of 12 required documents received.
5 Received
7 Pending
Contractual
5/7
LOA Issued
Yes
Agreement Signed
Yes
Escrow Agreement
Yes
Performance Bond
Yes
Contract Doc. Received
—
Insurance
—
Advance Bond
Yes
Technical
0/5
Source Approval Request
—
Drawings Submitted
—
Contractor Staff Details
—
Work Programme
—
Traffic Mgmt & Safety Plan
—
Contract Period Timeline
Scheduled Completion
2026-07-31
Duration Elapsed
148 / 91 days
Schedule Status
Overdue by 58 days
Project Completed
—
Completed Date
—
Mobilization
Planned vs Actual
Physical Progress25% vs 100%
Financial Progress17.6% vs 100%
Overall Progress
Overall
Planned: 100%
Behind by 75%
Financial Actual: 29.07 Mn / Planned 165.01 Mn
Behind 135.94 Mn
Critical Issues
In the process of Termination
Progress Breakdown
Structure Construction
0%
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 20.8% of contract
IPC 1 (Advance)
Paid
Swipe to see all certificate stages
1/20 used - next: IPC 2 as Advance
Advance Summary
Advance BondYes
Advance PaidYes
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 17.6% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
No IPC yet. Click Add IPC to create IPC 2 as IPC.
1/20 used - next: IPC 2 as IPC
Revised Contract
contract + approved VOs
Variation Order 1
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 2
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 3
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
Yes - projects.advance_bond
Bank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
Time
Elapsed - 58d overdue
Matale - Matale
Rehabilitation / Improvement of Wattegama Matale Road (5+280 - 13+160) and Ukuwela Railway station (0+000 - 0+190)
Project Name:
Project #33 - Contract No. RDA/DRP/CEN/MTL/MTL/33
Physical S-Curve - 2026-09-27 - Generated 2026-09-27 16:25
Contract No. RDA/DRP/CEN/MTL/MTL/33
Physical S-Curve - Planned vs Actual
Today: 2026-09-27 - 25%
Weekly Planned (Physical %)
Presentage
Actual financial
Matale - Matale
Rehabilitation / Improvement of Wattegama Matale Road (5+280 - 13+160) and Ukuwela Railway station (0+000 - 0+190)
Project Name:
Project #33 - Contract No. RDA/DRP/CEN/MTL/MTL/33
Financial S-Curve - 2026-09-27 - Generated 2026-09-27 16:25
Contract No. RDA/DRP/CEN/MTL/MTL/33
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-09-27 - LKR 29.07 Mn
Weekly Planned (Financial Mn)
02 May 2026
Today - 27 Sep 2026
30 Oct 2026
25% actual
81.8% time elapsed
Documents & Attachments
0 file(s) - up to 25 MB each
| Title |
Category |
Uploaded By |
Size |
Date |
Actions |
| No documents uploaded. |
Completion Forecast
Current pace
+1.4% / week
Estimated completion
2027-10-09
Weeks to 100%
53.3
Based on linear trend of your weekly progress snapshots.
Weekly Digest
Last snapshot
2026-09-25
Snapshot value
25%
Current progress
25%
Change
+1%
Project Notes
0
No notes yet. Add the first note to start the conversation.