Rehabilitation/Improvement of Nawalapitiya Ginigathena Road (B-319)(7+200-12+200)
NuwaraEliya - Central Province
Norwood
Jayawansa Construction (Pvt) Ltd
Timeline
-
91 days - 2026-06-17 -> 2026-09-15
Overdue 12d
Scheduled Completion
2026-09-15
93,758,217.76 LKR
RDA/DRP/CEN/NUE/NUR/97
14,149,694.34 LKR excl. VAT
15.1% of contract
12d overdue
102 / 91 days • 2026-06-17 -> 2026-09-15
Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceCentral Province
DistrictNuwaraEliya
EE DivisionNorwood
Package No.11
Tender ByRM&M
Scope
Contract NameRehabilitation/Improvement of Nawalapitiya Ginigathena Road (B-319)(7+200-12+200)
Estimated Road Lengths- km
Number of Roads0
Scope SummaryAsphalt overlay, Road Marking ,Retaining wall Construction,Drain Construction & Culvert Construction.
Contractor & Award
Contract No.RDA/DRP/CEN/NUE/NUR/97
Tender Batch No.10
Contractor NameJayawansa Construction (Pvt) Ltd
ConsultantNorwood EE
Tender StatusAwarded
LOA Date2026-05-19
Contract Amount93,758,217.76
Engineer Estimate Amount (LKR)104,490,700.33
Duration (Days)91
CategoryEmergency
Document Readiness
5 of 12 required documents received.
5 Received
7 Pending
Contractual
5/7
LOA Issued
Yes
Agreement Signed
Yes
Escrow Agreement
Yes
Performance Bond
Yes
Contract Doc. Received
—
Insurance
—
Advance Bond
Yes
Technical
0/5
Source Approval Request
—
Drawings Submitted
—
Contractor Staff Details
—
Work Programme
—
Traffic Mgmt & Safety Plan
—
Contract Period Timeline
Scheduled Completion
2026-09-15
Duration Elapsed
102 / 91 days
Schedule Status
Overdue by 12 days
Project Completed
—
Completed Date
—
Mobilization
Planned vs Actual
Physical Progress40% vs 100%
Financial Progress15.1% vs 100%
Overall Progress
Overall
Planned: 100%
Behind by 60%
Financial Actual: 14.15 Mn / Planned 93.76 Mn
Behind 79.61 Mn
Critical Issues
-
Progress Breakdown
Structure Construction
0%
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 17.8% of contract
IPC 1 (Advance)
Paid
Swipe to see all certificate stages
1/20 used - next: IPC 2 as Advance
Advance Summary
Advance BondYes
Advance PaidYes
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 15.1% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
No IPC yet. Click Add IPC to create IPC 2 as IPC.
1/20 used - next: IPC 2 as IPC
Revised Contract
contract + approved VOs
Variation Order 1
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 2
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 3
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
Yes - projects.advance_bond
Bank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
Time
Elapsed - 12d overdue
NuwaraEliya - Norwood
Rehabilitation/Improvement of Nawalapitiya Ginigathena Road (B-319)(7+200-12+200)
Project Name:
Project #97 - Contract No. RDA/DRP/CEN/NUE/NUR/97
Physical S-Curve - 2026-09-27 - Generated 2026-09-27 16:25
Contract No. RDA/DRP/CEN/NUE/NUR/97
Physical S-Curve - Planned vs Actual
Today: 2026-09-27 - 40%
Weekly Planned (Physical %)
Presentage
Actual financial
NuwaraEliya - Norwood
Rehabilitation/Improvement of Nawalapitiya Ginigathena Road (B-319)(7+200-12+200)
Project Name:
Project #97 - Contract No. RDA/DRP/CEN/NUE/NUR/97
Financial S-Curve - 2026-09-27 - Generated 2026-09-27 16:25
Contract No. RDA/DRP/CEN/NUE/NUR/97
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-09-27 - LKR 14.15 Mn
Weekly Planned (Financial Mn)
17 Jun 2026
Today - 27 Sep 2026
15 Dec 2026
40% actual
56.4% time elapsed
Documents & Attachments
0 file(s) - up to 25 MB each
| Title |
Category |
Uploaded By |
Size |
Date |
Actions |
| No documents uploaded. |
Completion Forecast
Current pace
+2.8% / week
Estimated completion
2027-03-01
Weeks to 100%
21.4
Based on linear trend of your weekly progress snapshots.
Weekly Digest
Last snapshot
2026-09-25
Snapshot value
40%
Current progress
40%
Change
+0%