Ditwah (CP) Awarded

RDA/DRP/CEN/KDY/KUN/20

Rehabilitation / Improvement to Structures on Madolkelle - Kabaragala - Kandenuwara Road (B 257) (4+000 - 8+000)

Kandy - Central Province Kundasale Samindra Construction
Progress -34.2% vs plan
29%
Complete
Planned63.2%
Time58%
49 days left - 69/119d
Timeline
LOA
2026-07-06
Possession
2026-07-20
Commencement
2026-07-20
Scheduled Completion
2026-11-15
Original Contract

31,558,227.98 LKR

RDA/DRP/CEN/KDY/KUN/20

Total Certified

— LKR excl. VAT

0% of contract

Overall Progress

29%

-34.2% vs planned
Plan 63.2%
Schedule

49 days left

58% time

69 / 119 days • 2026-07-20 -> 2026-11-15

Swipe tabs to see all sections — tap to switch

Planned

63.2%

Actual

29%

Presentage

-34.2%

Time Elapsed

58%

Days Left

49

Location & Package
ProvinceCentral Province
DistrictKandy
EE DivisionKundasale
Package No.1
Tender By-
Scope
Contract NameRehabilitation / Improvement to Structures on Madolkelle - Kabaragala - Kandenuwara Road (B 257) (4+000 - 8+000)
Estimated Road Lengths- km
Number of Roads0
Scope SummaryConstruction of Retaining wall and Gabion wall
Contractor & Award
Contract No.RDA/DRP/CEN/KDY/KUN/20
Tender Batch No.-
Contractor NameSamindra Construction
ConsultantTeam Leader
Tender StatusAwarded
LOA Date2026-07-06
Contract Amount31,558,227.98
Engineer Estimate Amount (LKR)28,660,618.70
Duration (Days)119
CategoryEmergency