Improvement to Damaged Road Section on Weeragantota - Randenigala Road. (From CH 19+000 To CH 27+200)
Kandy - Central Province
Kundasale
SD Civil Construction (Pvt) Ltd
Timeline
-
182 days - 2026-03-25 -> 2026-09-23
Overdue 4d
Scheduled Completion
2026-09-23
224,968,435.78 LKR
RDA/DRP/CEN/KDY/KUN/22
74,931,854.82 LKR excl. VAT
33.3% of contract
4d overdue
186 / 182 days • 2026-03-25 -> 2026-09-23
Swipe tabs to see all sections — tap to switch
Location & Package
ProvinceCentral Province
DistrictKandy
EE DivisionKundasale
Package No.3
Tender By-
Scope
Contract NameImprovement to Damaged Road Section on Weeragantota - Randenigala Road. (From CH 19+000 To CH 27+200)
Estimated Road Lengths- km
Number of Roads0
Scope SummaryGabion Wall Construction and Asphlt Overlaying
Contractor & Award
Contract No.RDA/DRP/CEN/KDY/KUN/22
Tender Batch No.4
Contractor NameSD Civil Construction (Pvt) Ltd
ConsultantTeam Leader
Tender StatusAwarded
LOA Date2026-03-12
Contract Amount224,968,435.78
Engineer Estimate Amount (LKR)333,005,906.52
Duration (Days)182
CategoryEmergency
Document Readiness
5 of 12 required documents received.
5 Received
7 Pending
Contractual
5/7
LOA Issued
Yes
Agreement Signed
Yes
Escrow Agreement
Yes
Performance Bond
Yes
Contract Doc. Received
—
Insurance
—
Advance Bond
Yes
Technical
0/5
Source Approval Request
—
Drawings Submitted
—
Contractor Staff Details
—
Work Programme
—
Traffic Mgmt & Safety Plan
—
Contract Period Timeline
Scheduled Completion
2026-09-23
Duration Elapsed
186 / 182 days
Schedule Status
Overdue by 4 days
Project Completed
—
Completed Date
—
Mobilization
Planned vs Actual
Physical Progress45% vs 100%
Financial Progress17.9% vs 100%
Overall Progress
Overall
Planned: 100%
Behind by 55%
Financial Actual: 40.19 Mn / Planned 224.97 Mn
Behind 184.78 Mn
Variation Orders: 31,522,538.00 / Contract incl. VOs 256,490,973.78
VO
Critical Issues
-
Progress Breakdown
Structure Construction
28%
Advance Pending
certified, not yet paid - incl. VAT
Advance Paid
incl. VAT - 21.1% of contract
IPC 1 (Advance)
Paid
Swipe to see all certificate stages
2/20 used - next: IPC 3 as Advance
Advance Summary
Advance BondYes
Advance PaidYes
IPC Paid - excl. VAT
exclusive VAT
IPC Pending - excl. VAT
certified, not yet paid - excl. VAT
Total Paid (IPC + Adv) - excl. VAT
of contract 17.9% - excl. VAT
Total Paid (IPC + Adv) - incl. VAT
incl. VAT
IPC 2 (IPC)
PD Certified
Swipe to see all certificate stages
2/20 used - next: IPC 3 as IPC
Revised Contract
contract + approved VOs
Variation Order 1
Prior Approval Sent
ReasonTore Steel R/F Quantity Exceed, Backfill material Quantity is exceed, Excavation Quantity Exceed
AmountLKR 31,522,538.00
Prior Approval SendYes
Approved—
Variation Order 2
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Variation Order 3
Not raised
Reason-
AmountLKR 0.00
Prior Approval Send—
Approved—
Effective Expire
issued — -> expire —
Advance Bond - Details (from bonds.xlsx)
Yes - projects.advance_bond
Bank-
Security Number-
Amount (Rs.)-
Bond Management By-
Issued Date—
Expire Date—
Extended—
Effective Expire- (released or not set)
ReleasedNo
Remarks-
Login with full edit rights to manage this bond.
Presentage
Actual physical
Time
Elapsed - 4d overdue
Kandy - Kundasale
Improvement to Damaged Road Section on Weeragantota - Randenigala Road. (From CH 19+000 To CH 27+200)
Project Name:
Project #22 - Contract No. RDA/DRP/CEN/KDY/KUN/22
Physical S-Curve - 2026-09-27 - Generated 2026-09-27 16:26
Contract No. RDA/DRP/CEN/KDY/KUN/22
Physical S-Curve - Planned vs Actual
Today: 2026-09-27 - 45%
Weekly Planned (Physical %)
Presentage
Actual financial
Kandy - Kundasale
Improvement to Damaged Road Section on Weeragantota - Randenigala Road. (From CH 19+000 To CH 27+200)
Project Name:
Project #22 - Contract No. RDA/DRP/CEN/KDY/KUN/22
Financial S-Curve - 2026-09-27 - Generated 2026-09-27 16:26
Contract No. RDA/DRP/CEN/KDY/KUN/22
Financial S-Curve - Planned vs Actual (LKR Mn)
Today: 2026-09-27 - LKR 40.19 Mn
Weekly Planned (Financial Mn)
25 Mar 2026
Today - 27 Sep 2026
24 Mar 2027
45% actual
51.1% time elapsed
Documents & Attachments
0 file(s) - up to 25 MB each
| Title |
Category |
Uploaded By |
Size |
Date |
Actions |
| No documents uploaded. |
Completion Forecast
Current pace
+1.8% / week
Estimated completion
2027-05-15
Weeks to 100%
30.2
Based on linear trend of your weekly progress snapshots.
Weekly Digest
Last snapshot
2026-09-25
Snapshot value
45%
Current progress
45%
Change
+1%
Project Notes
0
No notes yet. Add the first note to start the conversation.