Ditwah (CP) Awarded

RDA/DRP/CEN/MTL/MTL/41

Rehabilitation / Improvement of Matale Illukkumbura Laggala Road (B 274) (4+000 - 18+000)

Matale - Central Province Matale Vikum Construction
Progress -4.7% vs plan
6%
Complete
Planned10.7%
Time13.7%
156 days left - 25/182d
Timeline
LOA
2026-08-14
Possession
2026-09-02
Commencement
2026-09-02
Scheduled Completion
2027-03-02
Original Contract

276,683,432.37 LKR

RDA/DRP/CEN/MTL/MTL/41

Total Certified

— LKR excl. VAT

0% of contract

Overall Progress

6%

-4.7% vs planned
Plan 10.7%
Schedule

156 days left

13.7% time

25 / 182 days • 2026-09-02 -> 2027-03-02

Swipe tabs to see all sections — tap to switch

Planned

10.7%

Actual

6%

Presentage

-4.7%

Time Elapsed

13.7%

Days Left

156

Location & Package
ProvinceCentral Province
DistrictMatale
EE DivisionMatale
Package No.11
Tender By-
Scope
Contract NameRehabilitation / Improvement of Matale Illukkumbura Laggala Road (B 274) (4+000 - 18+000)
Estimated Road Lengths- km
Number of Roads0
Scope SummaryEarth works, base and shoulder work surface application, construction of drainage structures, construction of retaining structures and culvert construction
Contractor & Award
Contract No.RDA/DRP/CEN/MTL/MTL/41
Tender Batch No.-
Contractor NameVikum Construction
ConsultantMatale EE
Tender StatusAwarded
LOA Date2026-08-14
Contract Amount276,683,432.37
Engineer Estimate Amount (LKR)265,809,486.28
Duration (Days)182
CategoryEmergency